Quarterly Activities Report - June 2015
Released
Released
Announcement PDF
Quarterly Report
for the period ending 30 June 2015
Venture Fast Facts
Highlights
Venture advances Southeast Asian Initiative following the
receipt of granted tenure in northern Thailand
Riley DSO Project environmental approvals upheld following
dismissal of Federal Court appeal
Substantial cost cutting over the past year has resulted in the
Company maintaining a strong cash position of $3.3m
Riley DSO Project on hold but remains ready and well positioned
should future iron ore prices support a production decision
Introduction
The June Quarter saw Venture significantly advance opportunities in Southeast
Asia following the receipt of granted tenure in northern Thailand. The first two
prospects named “Pak Yang” and “Thali” are located in the highly prospective
Loei Belt, which already hosts world class copper and gold deposits. First pass
exploration on both prospects is currently underway.
The June Quarter also saw the Federal Court dismiss the appeal against the
environmental approvals for the Riley DSO Project. The decision effectively
delivers Venture unencumbered approvals for any future development of the
Riley iron ore mine. Following the favourable court decision, Venture will actively
seek to recover all legal costs.
ASX Code: VMS
Shares on Issue: 287 million
Market Cap: $6.3 million
Current Cash: $3.3 million
(30 June 2015)
Recent Announcements
Riley DSO Project Approvals
Upheld
(26/06/2015)
Copper Prospects Granted in
Southeast Asia
(18/05/2015)
Exploration success defines
additional target | Mt Lindsay
(19/11/2014)
EM defines New Targets
(23/10/2014)
Riley DSO Project Update
(19/08/2014)
Mining Lease Granted - Mt
Lindsay Tin/Tungsten Project
(03/07/2014)
Riley DSO Project Update
(11/06/2014)
Riley DSO Project
Appeal Lodged to Federal
Court Judgement
(06/06/2014)
Riley DSO Project
Federal Court Challenge
Dismissed
(16/05/2014)
Following a series of substantial cost cutting measures over the past year,
including up to 50% voluntary salary reductions for directors, management and
staff, the Company is now in a strong position and able to fund a series of
exploration programs in Thailand from its current cash reserves of $3.3m.
Federal Environment Minister
Approves Riley DSO Project
(5/8/13)
During the quarter the Company continued to keep the Riley DSO Project on hold
due to the sharp fall in iron ore prices over the past 12 months. However, the
Company has completed extensive pre-production work at the Riley Project
affording Venture the opportunity to commence production, on relatively short
notice, should future iron ore prices support a production decision.
Riley DSO Project Receives
EPA Approval and Conditions
(16/5/13)
Venture Minerals Limited
PO BOX 8234 Subiaco East WA 6008
288 Churchill Avenue Subiaco WA 6008
Telephone: +61 8 9381 4222
Fax: +61 8 9381 4211
ACN 119 678 385
ABN 51 119 678 385
Capital Items Secured and
Mining Contract Signed
(2/7/13)
W: www.ventureminerals.com.au
E: info@ventureminerals.com.au
Mt Lindsay Project, North West Tasmania
Introduction
The Mt Lindsay Project (186km2) is located in north-western Tasmania (refer to Figure 1) within the contact
metamorphic aureole of the highly perspective Meredith Granite. The project sits between the world class Renison
Bell Tin Mine (Metals X Ltd/Yunnan Tin Group-231kt of tin metal produced since 1968) and the Savage River
Magnetite Mine (operating for > 45 years, currently producing approximately 2.3 Mtpa of iron pellets). Mt Lindsay
has excellent access to existing infrastructure including hydro-power, water, sealed roads, rail and port facilities.
Venture owns 100% of the tenure that hosts both the Mt Lindsay Tin-Tungsten Deposit and all of the surrounding
prospects.
Figure 1 | Location Map for Mt Lindsay Tin-Tungsten Deposit/Riley DSO Deposit/Livingstone DSO Deposit
Since commencing exploration on the project in 2007, Venture has completed approximately 83,000m of diamond
core drilling at Mt Lindsay and defined a JORC compliant Measured, Indicated and Inferred Resources.
Page 2 of 10
Tin-Tungsten Resources
Table 1 | Tin-Tungsten Resources October 2012
Lower
Cut
(Tin
equiv)
0.20%
0.45%
Tin
Grade
Tungsten
Grade
(WO3)
Mass
Recovery
of
Magnetic
Iron (Fe)
Grade
Copper
Grade
Contained
Tin Metal
(tonnes)
Contained
Tin/
Tungsten
Metal
(tonnes)
Category
Tonnes
Tin
Equiv.
Grade
Measured
8.1Mt
0.6%
0.2%
0.1%
17%
0.1%
18,000
29,000
Indicated
17Mt
0.4%
0.2%
0.1%
15%
0.1%
32,000
43,000
Inferred
20Mt
0.4%
0.2%
0.1%
17%
0.1%
32,000
41,000
TOTAL
45Mt
0.4%
0.2%
0.1%
17%
0.1%
81,000
113,000
Measured
4.3Mt
0.8%
0.3%
0.2%
18%
0.1%
12,000
22,000
Indicated
5.2Mt
0.7%
0.3%
0.2%
15%
0.1%
14,000
22,000
Inferred
3.9Mt
0.6%
0.3%
0.1%
9%
0.1%
12,000
17,000
TOTAL
13Mt
0.7%
0.3%
0.2%
14%
0.1%
38,000
61,000
Note: Reporting to two significant figures. Figures have been rounded and hence may not add up exactly to the given totals. Full
details of the estimate are in the ASX announcement for the Quarterly Report on 17 October 2012.
Notes:
The Sn equivalent formula used to calculate the Sn equivalent values for the Main and No.2 Skarns is as follows: Sn Equivalent (%) =
Sn% + (WO3% x 1.90459) + (mass recovery % of magnetic Fe x 0.006510) + (Cu% x 0.28019). Whereas for the Sn equivalent formula
used to calculate the Sn equivalent values for the Stanley River South and Reward Skarns is as follows: Sn Equivalent (%) = Sn% +
(WO3% x 1.65217) + (Cu% x 0.34783).
The mass recovery of the magnetic iron is determined mostly by Davis Tube Results (“DTR”).
The Sn equivalent formulae uses a tin metal price of US$23,000/t, an APT (Ammonium Para Tungstate) price of US$380/mtu (1mtu
=10kgs of WO3), a magnetite concentrate price of US$110/t and a copper metal price of US$8,000/t.
Pilot scale metallurgical testwork has been completed on the Main and No.2 Skarns with results indicating the metallurgical recovery
for tin is 72%, for WO3 is 83%, for iron in the form of magnetite is 98% and for copper is 58%. The results of this testwork are stated in
the ASX announcement of August 31 2012.
It is the Company’s opinion that the tin, WO3 and copper as included in the metal equivalent calculations for the Stanley River South and
Reward Skarns have a reasonable potential to be recovered for when the Mt Lindsay Project goes into production.
The resource base at Mt Lindsay is hosted within two magnetite rich skarns (Main Skarn and the No.2 Skarn) which
extend over a total strike of 2.8kms and remain open at depth. Additional indicated and inferred resources have
been defined at the Reward and Stanley River South Prospects, which extend over an additional 1.1km of strike.
Page 3 of 10
In 2012 the resource base at Mt Lindsay was the subject of a Bankable Feasibility Study (“BFS”) which entertained
a 1.75 million tonne per annum operation, producing concentrates of tin, tungsten, copper and magnetite. The study
delivered an NPV8 of A$143m from a 9 year mine life with a capital cost estimate of A$198m. Full details of the
reserve statement and BFS outputs and a list of assumptions are in the ASX announcement of 7 November 2012.
Over the past 12 months Venture has focussed efforts at Mt Lindsay on identifying additional high grade
tin/tungsten targets in close proximity to the Mt Lindsay Deposit. The low cost exploration work is part of a broader
strategy focussed on identifying high grade mineralization within trucking distance of the existing deposit that has
the potential to further strengthen the economics of the Mt Lindsay Project.
Activities during the June Quarter
In recent quarters Venture has successfully defined eight new targets considered prospective for high grade
tin/tungsten mineralization as well as targets prospective for copper and nickel mineralization (refer to Figure 2).
These targets are hosted within the broader skarn units identified throughout the Mt Lindsay area of which to date
only 10% have been drill tested.
During the June Quarter Venture continued to work on identifying new target areas in close proximity to the Mt
Lindsay Deposit which included geological mapping in the Stanley River area.
Figure 2 | Mt Lindsay - recently identified exploration targets
Page 4 of 10
Riley DSO Hematite Project, North West Tasmania
The 100% owned Riley DSO Project is located 10km from the Mt Lindsay Project (refer to Figure 1) and occurs as a
hematite rich pisolitic and cemented laterite. The deposit is all at surface, located less than two kilometres from a
sealed road that accesses existing rail and port facilities.
A maiden resource statement of 2mt @ 57% Fe was defined in 2012 which resulted in the Company doubling its
overall DSO resource base, including the Livingstone Deposit, to 4.4mt @ 57% Fe.
Table 2 | Resource Statement - Riley DSO Project
Resource
Tonnes
Fe (%)
Fe (%)
Calcined
SiO2 (%)
Al2O3 (%)
P (%)
S (%)
Cr (%)
LOI
(%)
Indicated
2.0mt
57
61
3.7
2.6
0.03
0.08
2.8
7.7
*Refer to ASX announcement on 26 July 2012.
Following completion of the resource Venture engaged independent mining engineers, Rock Team to complete
mining studies on the deposit and produce a reserve statement. With all the hematite resources at Riley located at
or near surface, the study delivered a 90% conversion rate of resource to reserve.
Table 3 | Reserve Statement - Riley DSO Project
Reserve
Tonnes
Fe (%)
Fe (%)
Calcined
SiO2 (%)
Al2O3 (%)
P (%)
S (%)
Cr (%)
LOI
(%)
Probable
1.8mt
57
61
3.7
2.6
0.03
0.07
2.8
7.8
*Refer to ASX announcement on 26 July 2012.
Activities during the June Quarter
During the quarter the Federal Court dismissed the appeal against the environmental approvals for the Riley DSO
Project. The decision effectively delivers Venture unencumbered approvals for any future development of the Riley
iron ore mine. The Federal Court decision in both the original case and the recent appeal awarded costs in favour
of Venture. The Company will continue to actively seek the recovery of all legal costs associated with both cases.
During the quarter the Riley DSO Project remained on hold due to the sharp fall in iron ore prices over the past 12
months. Although the Company made the decision to suspend operations in August last year, Venture had already
completed extensive pre-production work at the Riley Project putting in place all the necessary requirements to
commence mining. This work has placed Venture in a strong position should the iron ore price improve and afford
the Company the opportunity to commence production with relatively short notice.
Page 7 of 8
Livingstone DSO Hematite Project, North West Tasmania
Located only 3.5km from the Company’s flagship Mt Lindsay Tin-Tungsten Deposit is the 100% owned Livingstone
DSO Hematite Deposit (refer to Figure 1). Livingstone consists of an outcropping hematite cap overlaying a magnetite
rich skarn. The hematite occurs from surface, is consistent in grade and located only 2km from a sealed road which
accesses existing rail and port facilities.
A maiden resource statement of 2.2mt @ 58% Fe was defined at Livingstone in 2011, which was followed by a
positive and robust scoping study. Additional work later in 2011 included blending and sizing testwork and
preliminary mining studies, all of which delivered positive results.
During the second half of 2012 the Company completed a resource upgrade, which resulted in 100% of the inferred
resources being converted to the indicated category.
Table 4 | Resource Statement Livingstone DSO Project
Resource
Tonnes
Fe (%)
Fe (%)
Calcined
SiO2 (%)
Al2O3 (%)
P (%)
S (%)
LOI (%)
Indicated
2.4mt
57
61
5.4
1.9
0.07
0.05
7.0
*Refer to ASX announcement on 26 July 2012.
Immediately following the resource upgrade Venture engaged independent mining engineers, Rock Team to
complete mining studies on the deposit and produce a reserve statement. With the hematite resources at Livingstone
consistent in nature and outcropping at surface the study delivered a 90% conversion rate of resource to reserve.
Table 5 | Reserve Statement - Livingstone DSO Project
Reserve
Tonnes
Fe (%)
Fe (%)
Calcined
SiO2 (%)
Al2O3 (%)
P (%)
S (%)
LOI (%)
Probable
2.2mt
57
62
5.3
1.9
0.08
0.03
7.1
*Refer to ASX announcement on 26 July 2012.
Activities during the June Quarter
There was no field activity during the quarter.
Page 8 of 8
South East Asia Initiative
Venture continues to progress its strategy of targeting South East Asia for exploration opportunities. Venture has
identified an extensive belt of “skarn style” mineralisation throughout the region specifically targeting strategic
metals such as tin and tungsten as well as other base and precious metals.
The Company has established a low cost regional office in the region and will look to continue to build a cost effective
portfolio of exploration projects over the medium term.
The June Quarter saw Venture significantly advance opportunities in Southeast Asia following the receipt of granted
tenure in northern Thailand. The first two prospects named “Pak Yang” and “Thali” are located in the highly
prospective Loei Belt, which already hosts world class copper and gold deposits including Kingsgate’s “Chatree”
deposit (+5Moz Au*) and PanAust’s “Phu Kham” deposit (1.3Mt Cu, 1.8Moz Au*) (refer to Figure 3).
Work commenced late in the quarter at both the Thali and Pak Yang prospects, which already host identified “skarn”
style mineralization. The on-going work programs include detailed geological mapping, rock chip sampling and a first
pass soil sampling program.
Figure 3 | Prospect location map - Thailand
Page 9 of 8
Harris Bluff Project, South Australia
Venture has withdrawn from the joint venture on the Harris Bluff Project.
Detailed information on all aspects of Venture Minerals’ projects can be found on the Company’s website
www.ventureminerals.com.au.
Yours faithfully
Hamish Halliday
Managing Director
The information in this report that relates to Exploration Results and Exploration Targets is based on information compiled by Mr Andrew Radonjic, a full time employee of the
company and who is a Member of The Australasian Institute of Mining and Metallurgy. Mr Andrew Radonjic has sufficient experience which is relevant to the style of mineralisation
and type of deposits under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the ‘Australasian Code for
Reporting of Exploration Results, Mineral Resources and Ore Reserves’. Mr Andrew Radonjic consents to the inclusion in the report of the matters based on his information in the
form and context in which it appears.
The information in this report that relates to Mineral Resources is based on information compiled by Mr Andrew Radonjic, a full time employee of the company and who is a Member
of The Australasian Institute of Mining and Metallurgy. Mr Andrew Radonjic has sufficient experience which is relevant to the style of mineralisation and type of deposits under
consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2004 Edition of the ‘Australasian Code for Reporting of Exploration Results,
Mineral Resources and Ore Reserves’. Mr Andrew Radonjic consents to the inclusion in the report of the matters based on his information in the form and context in which it appears.
It has not been updated since to comply with the JORC Code 2012 on the basis that the information has not materially changed since it was last reported.
The information in this report that relates to Ore Reserves is based on information compiled by Mr Denis Grubic, who is a Member of the Australasian Institute of Mining and
Metallurgy. Mr Grubic is an independent consultant employed by Rock Team Pty Ltd. Mr Grubic qualifies as a Competent Person as defined in the 2004 Edition of the ‘Australasian
Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’. Mr Grubic consents to the inclusion in the report of the matters based on his information in the form
and context in which it appears. . It has not been updated since to comply with the JORC Code 2012 on the basis that the information has not materially changed since it was last
reported.
Page 7 of 8
Appendix One| Tenements
Mining tenements held at the end of June 2015 quarter
Project
Location
Tenement
Interest at June 2015
Mount Lindsay
Tasmania
Tasmania
Tasmania
Tasmania
Tasmania
Tasmania
3M/2012
5M/2012
7M/2012
EL21/2005
EL45/2010
EL72/2007
100%
100%
100%
100%
100%
100%
Thali
Thailand
Thailand
70/2558
71/2558
100%
100%
Pak Yang
Thailand
69/2558
100%
Mining tenements acquired and disposed during the June 2015 quarter
Project
Location
Tenement
Interest at beginning
of quarter
Interest at end of
quarter
Mining tenements relinquished
Harris Bluff
South Australia
EL4788
51%
0%
Mining tenements acquired
Thali
Thailand
Thailand
70/2558
71/2558
0%
0%
100%
100%
Pak Yang
69/2558
0%
100%
Thailand
Beneficial percentage interests in joint venture agreements at the end of the quarter
Project
Location
Tenement
Interest at June 2015
Nil
Beneficial percentage interests in farm-in or farm-out agreements acquired or disposed of during
the quarter
Project
Location
Mining tenements relinquished
Harris Bluff
South Australia
Tenement
Interest at beginning
of quarter
Interest at end of
quarter
EL4788
51%
0%
Page 8 of 8