Quarterly Activities Report
for the period ending 30 June 2026
Critica Limited (ASX: CRI) (Critica or the Company) is pleased to provide its Quarterly Activities Report
for the period ending 30 June 2026.
Highlights from the Quarter
• Jupiter pilot plant optimisation delivered an intermediate concentrate grading
approximately 3% TREO – an approximate 14× upgrade – at approximately 90–95%
mass rejection
• Strong recoveries maintained: approximately 81% Magnet REO recovery and
approximately 71% TREO recovery from representative feed
• Third high-purity MREO produced at approximately 97% TREO; commercial-grade
MREC (approximately 58% TREO, ANSTO) and MREO (approximately 97% TREO, AMML)
product routes confirmed
• Approximately 63% gallium extraction demonstrated using the existing
hydrometallurgical flowsheet
• Jupiter resource optimisation completed; 145 infill holes for 7,265 metres finalised for
handover to SRK Consulting for an updated Mineral Resource Estimate
• DRA Global appointed to lead the Mt Lindsay Scoping Study on a low-impact, ESG-
aligned underground (paste/backfill) development basis
• Strengthening tin and tungsten prices and constructive engagement with Mineral
Resources Tasmania, including Ministerial support, reinforce Mt Lindsay’s value
potential
• Mt Lindsay resource update and geological modelling underway to assess extraction of
critical metals; partnership and offtake discussions progressing
• $300,000 in non-dilutive MRIWA and RTCM Trailblazer research funding secured;
Critica joined the U.S. Defense Industrial Base Consortium (DIBC) and the Critical
Minerals Association Australia (CMAA)
• Advancing a dual-project critical minerals platform spanning rare earths, yttrium,
gallium, tin and tungsten, with both Scoping Studies on track for completion during Q3
2026
• Strong cash position of $5.3m at end of quarter.
2
Critica’s CEO Jacob Deysel commented:
The June 2026 quarter reflected strong, balanced progress across both of Critica’s critical minerals
projects. At Jupiter, ongoing pilot plant optimisation delivered an intermediate concentrate grading
approximately 3% TREO – an approximate 14× upgrade – at approximately 90–95% mass rejection,
while maintaining approximately 81% Magnet REO and 71% TREO recovery. We also produced a third
high-purity Mixed Rare Earth Oxide at approximately 97% TREO and confirmed both commercial-grade
carbonate and oxide product routes, continuing to de-risk the project ahead of the Scoping Study.
At Mt Lindsay, we appointed DRA Global to lead a Scoping Study on a low-impact, ESG-aligned
underground development basis. Strengthening tin and tungsten markets and constructive
engagement with Mineral Resources Tasmania, including support at Ministerial level, have reinforced
the strategic value of one of the world’s largest undeveloped tin-tungsten projects, and resource
update and modelling work is now underway alongside partnership and offtake discussions. Jupiter
and Mt Lindsay are advancing in parallel as the two pillars of our dual-project critical minerals
platform, with both Scoping Studies targeted for completion during Q3 2026.
We further strengthened our strategic position through $300,000 in non-dilutive MRIWA and RTCM
Trailblazer research funding and membership of the U.S. Defense Industrial Base Consortium and the
Critical Minerals Association Australia (CMAA), reinforcing the growing strategic relevance of a
portfolio spanning rare earths, yttrium, gallium, tin and tungsten. With multiple workstreams
progressing across both projects, Critica believes it is entering an exciting period of value creation and
catalyst delivery.
Jupiter Rare Earths Project
Project Overview
Jupiter is Australia’s largest clay-hosted rare earth resource, comprising 1.8 billion tonnes at
approximately 1,700 ppm TREO at a 1,000 ppm cut-off, including 640 million tonnes at approximately
490 ppm high-value magnet rare earth oxide (MagREO) at a 400 ppm cut-off. The deposit is located
within the Mt Magnet and Yalgoo mining district in Western Australia, less than 10 kilometres from
the bitumen highway connecting Mt Magnet and Geraldton, providing ready access to the Port of
Geraldton, the mid-west gas pipeline and transmission infrastructure within 40 kilometres of site.
During the June 2026 quarter, Jupiter advanced across four mutually reinforcing workstreams,
including continued optimisation of the beneficiation-first flowsheet, production of a high-purity
Mixed Rare Earth Oxide, completion of resource optimisation ahead of an updated Mineral Resource
Estimate, and progression of the Scoping Study led by Sedgman. Together these outcomes continue to
de-risk the project and strengthen the technical foundation of the Scoping Study, which remains on
track for completion during Q3 2026.
3
Beneficiation Optimisation
A major focus during the quarter was continued optimisation of Jupiter’s beneficiation-first
development strategy. From a representative feed grade of approximately 2,137 ppm TREO, pilot plant
optimisation delivered an intermediate concentrate grading approximately 3% TREO – an approximate
14× upgrade – at approximately 90–95% mass rejection, concentrating the rare earth minerals into
around 5% of the original feed mass.
Key outcomes achieved during the quarter include:
• Up to 14× upgrade factor to an intermediate concentrate grading approximately 3% TREO
• Approximately 81% Magnet REO recovery
• Approximately 71% TREO recovery
• Approximately 90–95% mass rejection
• Strong Magnet Rare Earth recoveries maintained – Nd₂O₃ 74.5%, Dy₂O₃ 74.7%, Pr₆O₁₁ 69.3%
and Tb₄O₇ 65.9%
Pilot-scale beneficiation operations resumed following the Lunar New Year period and have been
relocated to a larger facility in Hai Phong to support expanded throughput and further optimisation.
These results continue to strengthen confidence in the scalability of the flowsheet while supporting
improved development assumptions for the Jupiter Scoping Study.
Commercial-Grade Rare Earth Products
Critica has now successfully produced both commercial-grade Mixed Rare Earth Carbonate (MREC) and
Mixed Rare Earth Oxide (MREO) from Jupiter. During the quarter, a third high-purity MREO grading
approximately 97% Total Rare Earth Oxide (TREO) was independently produced by Australian Mineral
and Metallurgical Laboratories Pty Ltd (AMML), representing a significant step-change on the 84% and
86% TREO products reported in prior quarters (refer to ASX announcements 28 October and 2
December 2025).
The latest testwork delivered total rare earth recoveries of up to approximately 71% and Magnet Rare
Earth (Nd, Pr, Dy, Tb) recoveries of up to approximately 76% at the hydrometallurgical stage. Together
with the commercial-grade MREC grading approximately 58% TREO produced by ANSTO using a
conventional sulphuric acid bake flowsheet, these results validate multiple product routes,
demonstrate the flexibility of the Jupiter flowsheet and represent an important milestone in the
project’s development pathway. Key characteristics of the ANSTO MREC are summarised in Table 1
below.
MREC Product Specification
The MREC produced by ANSTO delivered a Total Rare Earth Oxide (TREO) grade of 57.82%, placing
Jupiter at the upper end of grades reported for development-stage mixed rare earth carbonate
products. Key product characteristics are summarised in Table 1 below.
4
Table 1: | MREC key product characteristics (refer to ASX announcement 16 February 2026)
Component Unit MREC Result
TREO wt% 57.82
MREO (Nd, Pr, Dy, Tb) wt% 14.1
MREO/TREO wt% 24.4%
LREO wt% 55.4
HREO wt% 2.41
Al₂O₃ wt% 0.89
Fe₂O₃ wt% 0.08
Na₂O wt% 1.32
P₂O₅ wt% 0.22
SO₄ wt% 2.25
U₃O₈ ppm 51
ThO₂ ppm 13
Recovery and Process Performance
The ANSTO testwork employed a conventional sulphuric acid bake flowsheet comprising sulphuric acid
bake, water leach, two-stage impurity removal and MREC precipitation using a carbonate-based
reagent. Key recovery outcomes:
• Cumulative step-through recovery to MREC of approximately 80.3% TREO
• In a commercial operating circuit, recycling of IR-2 solids would recover rare earths currently
reporting to that stream, increasing projected overall recovery to approximately 89% TREO
• Effective iron and phosphorus rejection achieved through optimised impurity removal
conditions, reducing downstream rare earth co-precipitation losses
These results confirm the technical viability of a conventional sulphuric acid bake flowsheet for Jupiter
as a baseline processing pathway, while broader processing options continue to be evaluated as part
of the Scoping Study. The acid addition range and bake parameters applied are within typical ranges
used for rare earth phosphate concentrates.
Integrated Beneficiation-First Processing Pathway
Critica’s development approach integrates upfront beneficiation with conventional downstream
hydrometallurgical processing. The beneficiation-first strategy has now demonstrated the ability to
reject approximately 90–95% of mass and upgrade feed to an intermediate concentrate grading
approximately 3% TREO (an approximate 14× upgrade), significantly reducing downstream processing
volume, reagent intensity and capital requirements, with ongoing optimisation workstreams focused
on further refining performance. Both MREC and MREO product pathways have now been
demonstrated, confirming optionality for the downstream configuration.
5
Product and Market Positioning
With commercial-quality MREC and MREO now demonstrated, Critica is advancing the preparation of
representative product samples for qualification with downstream separation plants and refining
groups. The Company is progressing early-stage engagement with potential offtake counterparties,
aligning product specifications with refinery requirements as part of the Scoping Study execution
pathway. MREC and MREO are commonly traded intermediate products within the rare earth supply
chain, positioned higher in the value chain than mineral concentrates, reflecting its increased rare
earth content and suitability for downstream refining.
Metallurgical Optimisation - Ongoing Workstreams
Further optimisation work is advancing in parallel across multiple institutions, focused on:
• Reagent consumption optimisation across acid bake, impurity removal and solid–liquid
separation stages
• Recovery enhancement and impurity management to further reduce already-low impurity
levels
• Refinement of operating parameters
• Assessment of alternative process pathways to support capital and operating efficiency
Metallurgical programmes are advancing with ANSTO, GAVAQ, Minutech–AMML and Phenikaa
University. Sedgman is providing integrated process engineering and development support, bringing
extensive rare earth project experience across multiple optimisation streams progressed in parallel.
GAVAQ Pilot Plant - Beneficiation (Closed Circuit)
Pilot-scale beneficiation operations at GAVAQ resumed following the Lunar New Year period and have
been relocated to a larger facility in Hai Phong, supporting expanded throughput capacity, improved
cell configurations and further optimisation of operating conditions. The pilot continues to generate
decision-grade datasets – recoveries, concentrate specifications, reagent consumption and operability
metrics – that feed directly into Scoping Study engineering workstreams.
Additional representative Jupiter mineralisation is being dispatched to the pilot facility to support
continued optimisation and the production of intermediate concentrate for MREO sample generation,
product qualification and offtake discussions.
Gallium and Co-Product Opportunities
While rare earths remain the primary focus of development at Jupiter, ongoing metallurgical
programmes continue to highlight the potential for additional value from co-products within the
broader mineral system. Previous testwork demonstrated approximately 63% gallium extraction into
solution using the same hydrometallurgical flowsheet developed for rare earth recovery, and Jupiter
currently hosts approximately 70,000 tonnes of contained gallium (refer to ASX announcement 17
November 2025). Critica is working with a specialist downstream group to assess potential gallium
6
product pathways and market opportunities, while beneficiation programmes continue to produce an
iron-rich concentrate stream that is being assessed for potential applications.
Product Qualification and Offtake Preparation
With both MREC and MREO pathways demonstrated, Critica has commenced preparation of
representative product samples for qualification and commercial engagement. This process includes
the production of intermediate concentrate at GAVAQ, generation of representative product samples,
product qualification programmes and early-stage downstream engagement. These activities
represent an important transition from technical validation toward commercial evaluation and market
engagement.
Resource Update
Resource optimisation remained a key focus of ongoing Scoping Study activities during the quarter.
Since publication of the initial Mineral Resource Estimate, Critica has completed 145 infill drill holes
for 7,265 metres at Jupiter, together with a further 29 holes for 1,204 metres at Juno and additional
drilling across regional targets including Aurora. The programme targeted higher-grade zones within
the existing resource and is supporting evaluation of selective mining opportunities and higher-grade
feed strategies as part of ongoing Scoping Study development.
Updated Mineral Resource Estimate
Data validation, geological interpretation and resource optimisation work were substantially
completed during the quarter and finalised for handover to SRK Consulting Australasia for resource
estimation. The updated Mineral Resource Estimate will support ongoing mine planning and Scoping
Study activities and will be released following completion of SRK’s work.
SRK Consulting is undertaking the updated Jupiter Mineral Resource model, integrating the new drilling
data into the ongoing Scoping Study.
Regional Growth Opportunities
Recent drilling at Juno and Aurora continues to highlight the broader growth potential of the district-
scale Brothers Project. Initial results of the WA Government Exploration Incentive Scheme (EIS) co-
funded drilling programme recently completed at Juno are expected in the near term.
Juno
Juno is a high-priority regional target located south of the Jupiter deposit within the Brothers Project.
The programme comprises approximately 30 AC holes testing priority targets within an approximate
2km x 500m corridor. Mineralisation at Juno is characterised by a higher proportion of magnet rare
earth oxides (MagREO), and the programme is evaluating potential for higher-value REE product
streams within the Brothers system.
7
Aurora
Aurora is a regional prospect located northwest of Jupiter, where prior drilling identified clay-hosted
REE mineralisation associated with a discrete aeromagnetic anomaly. The programme comprises
approximately 28 AC holes following up 2024 regional drilling results, testing mineralisation continuity
across an approximate 2km x 500m corridor targeting mineralisation analogous to Jupiter.
Scoping Study Progress
The Jupiter Scoping Study, led by Sedgman with Snowden Optiro (mining inputs) and SRK Consulting
(resource updates), progressed rapidly during the quarter, integrating the significant technical
advances achieved across resource optimisation, beneficiation, hydrometallurgical testwork and
product qualification. The strong beneficiation performance and production of commercial-grade rare
earth products have the potential to materially enhance project economics relative to earlier
development concepts. The Scoping Study remains on track for completion during Q3 2026, and is led
by the following specialist consultants:
• Sedgman - Lead study management and process integration
• Snowden Optiro - Mining and scheduling
• SRK Consulting - Resource update and optimisation
The Scoping Study integrates beneficiation, downstream processing, infrastructure and development
assumptions to define a base-case development pathway. The resource upgrade drilling programme,
MREC and MREO production results, GAVAQ pilot plant data and ongoing metallurgical optimisation
workstreams all feed directly into the Scoping Study.
Sustainability Profile
Critica continued to advance sustainability-related workstreams during the quarter through the
progression of pilot-scale beneficiation, downstream hydromet programmes and Scoping Study inputs.
The beneficiation-first development pathway supports a more compact and efficient processing
footprint with potential for lower reagent, energy and water intensity.
Jupiter’s clay-hosted mineralisation continues to exhibit consistently low in-situ uranium and thorium,
favourable for permitting and logistics. The confirmed ability to recover multiple critical minerals - rare
earths and gallium (figure 1) - through a single integrated flowsheet enhances resource efficiency and
alignment with Western critical-materials supply chain objectives.
8
Figure 1: | Resource Model – showing Ga₂O₃ grade distribution across the resource model
Brothers Project
Exploration and Field Work
During the quarter, field activities advanced with the commencement of resource upgrade and
regional drilling across the Brothers Project area. The drilling programmes at Jupiter, Juno and Aurora
represent the primary exploration and resource advancement activities for the period, as detailed in
the Resource Upgrade & Regional Drilling section above.
The broader Brothers Project area continues to demonstrate potential for additional resource growth.
Regional drilling at Juno and Aurora is assessing mineralisation continuity and scale beyond the current
Jupiter footprint, with the Juno target characterised by elevated magnet rare earth oxide proportions
and the Aurora target testing mineralisation analogous to Jupiter.
Mt Lindsay - Tin & Tungsten Project, Tasmania
Mt Lindsay is one of the world’s largest undeveloped tin-tungsten projects, hosting approximately
81,000 tonnes of contained tin and 3.2 million tonne units of WO₃ (approximately 32,000 tonnes of
contained tungsten) within a granted Mining Lease (refer to ASX announcement dated 17 October
2012). The project sits within a world-class tin-tungsten province, remains open at depth and is
supported by more than 83,000 metres of historical diamond drilling and established export
infrastructure at the Port of Burnie in northwest Tasmania.
During the quarter, Critica appointed DRA Global to undertake a Scoping Study for Mt Lindsay,
evaluating a low-impact underground development strategy incorporating paste/backfill to reduce
surface tailings and infrastructure positioning aligned with ESG outcomes. The revised approach
9
repositions Mt Lindsay as an ESG-aligned critical minerals project complementary to Jupiter.
Government engagement remains constructive, with a recent meeting with Mineral Resources
Tasmania and positive Ministerial support. Resource update and geological modelling are underway.
Tin and tungsten prices continue to be supported by tightening global supply and export restrictions
introduced in November 2025, reinforcing the strategic value of Mt Lindsay within a supply-
constrained market. The Mt Lindsay Scoping Study, led by DRA Global, is on track for completion during
Q3 2026, with partnership and offtake discussions progressing.
Livingstone Project, Tasmania
After expiry of Mining Lease 3M/2012 the Livingstone Project area has been reverted to Exploration
Licence 21/2005, which allows Critica to continue to advance exploration, resource definition and
metallurgical activities as part of the broader Mt Lindsay development strategy.
Corporate
Strategic Partnerships and Funding
During the quarter, Critica secured $300,000 in non-dilutive funding – comprising a $150,000 MRIWA
award and $150,000 in RTCM Trailblazer funding – to accelerate metallurgical development at Jupiter,
including the investigation of alternative processing routes such as REE bioleach extraction. Critica also
joined the U.S. Defense Industrial Base Consortium (DIBC) and the Critical Minerals Association
Australia (CMAA), strengthening access to strategic partnerships, funding opportunities and critical
minerals supply chain initiatives. These initiatives reinforce the strategic relevance of Critica’s critical
minerals portfolio while preserving shareholder capital.
Investor Engagement
The Company continued its active investor engagement programme during the quarter, hosting an
investor webinar on 22 June 2026 at which CEO Jacob Deysel provided a live update on project
advancement across both assets. Investor relations activities are coordinated through Investability
Partners (Dannika Warburton, investors@investability.com.au). Investors are encouraged to register at
Critica’s Interactive Investor Hub to receive updates and engage directly with the investor relations
team.
Planned Work Programs - September 2026 Quarter
During the September 2026 quarter, Critica expects to advance the following key workstreams:
Resource & Drilling
• Release of the updated Jupiter Mineral Resource Estimate following completion of SRK
Consulting’s resource estimation
• Receipt of initial EIS co-funded regional drilling results from Juno
Metallurgy & Processing
• Further beneficiation and hydrometallurgical optimisation, including improvements to reagent
and acid consumption
10
• Continued production of intermediate concentrate and representative MREC and MREO
samples for downstream product qualification
• Progression of gallium and co-product evaluation programmes
Scoping Study
• Completion of the Jupiter Scoping Study with Sedgman (targeted during Q3 2026)
• Completion of the Mt Lindsay underground Scoping Study with DRA Global (targeted during
Q3 2026)
• Advancement of product qualification, offtake and strategic partnership discussions across
both projects
Additional Information Required by ASX Listing Rule 5.3
As at 30 June 2026, the Group held cash and cash equivalents of $5.3m, and notes the following
aggregate payments during the quarter:
• A$1.9m on exploration activities (refer to Item 1.2(a) of Appendix 5B), relating to drilling,
Jupiter metallurgical testwork, studies at Mt Lindsay and Jupiter, tenement fees and rates, and
geological staff costs (ASX Listing Rule 5.3.1)
• There were no mining or development activities during the quarter (ASX Listing Rule 5.3.2)
• A$74,000 in aggregate of payments made to related parties or their associates (refer to Item
6.1 of Appendix 5B), comprising Directors’ fees, salaries and superannuation (ASX Listing Rule
5.3.5)
Glossary of Terms
• TREO (Total Rare Earth Oxides): Sum of all rare earth oxide content in a sample, representing the sum
of 14 rare earth elements (excluding promethium) plus yttrium, expressed as oxides.
• MagREO (Magnet Rare Earth Oxides): The sum of neodymium (Nd₂O₃), praseodymium (Pr₆O₁₁),
dysprosium (Dy₂O₃) and terbium (Tb₄O₇), expressed as oxides. Primary value drivers for permanent
magnets used in electric vehicles, renewables and defence.
• MREC (Mixed Rare Earth Carbonate): A conventional intermediate product in the rare earth supply
chain, supplied to separation plants for further refining. Critica produced its first commercial-quality
MREC at 58% TREO at ANSTO in February 2026.
• MREO product (Mixed Rare Earth Oxide): A high-grade oxide intermediate produced via the acid-bake
route. Critica produced MREO products grading 84%, 86% and, in the June 2026 quarter, approximately
97% TREO (refer to ASX announcements 28 October 2025, 2 December 2025 and 18 May 2026).
• MREP (Mixed Rare Earth Products): Critica’s collective term covering both Mixed Rare Earth Carbonate
(MREC) and Mixed Rare Earth Oxide (MREO) product specifications.
• Beneficiation: Physical upgrading of ore by rejecting waste material (quartz, feldspar, iron oxides) while
concentrating the valuable rare earth minerals, typically ahead of hydrometallurgical treatment.
• EIS (Exploration Incentive Scheme): WA Government co-funded drilling programme that reimburses up
to 50% of eligible drilling and mobilisation costs for qualifying exploration programmes.
11
• Inferred Mineral Resource: A Mineral Resource for which quantity and grade are estimated with a low
level of confidence under the JORC Code (2012). Targeted for conversion to Indicated classification
through the current drilling programme.
• Indicated Mineral Resource: A Mineral Resource estimated with sufficient confidence to support mine
planning. A higher JORC Code classification than Inferred.
• Scoping Study: A preliminary economic and technical assessment of the viability of a mining project,
conducted prior to a Pre-feasibility Study.
Authorised by the Board of Critica Limited.
Jacob Deysel
Chief Executive Officer
Critica Limited
admin@critica.limited
Investor and Media Relations
Dannika Warburton
Investability Partners
investors@investability.com.au
JOIN CRITICA’S INTERACTIVE INVESTOR HUB
Sign up and engage with our investor relations team
BUILDING A CRITICAL MINERALS PLATFORM
RARE EARTHS | YTTRIUM | GALLIUM | TIN | TUNGSTEN
Critica Limited (ASX: CRI) is advancing a
portfolio of critical minerals projects with
exposure to commodities used in defence,
semiconductors, artificial intelligence,
advanced manufacturing and
electrification.
The Jupiter Project in Western Australia
provides exposure to rare earths, yttrium
and gallium, while the Mt Lindsay Project in
Tasmania provides exposure to tin and
tungsten.
Together, these projects provide exposure
to minerals essential to future industrial
growth and national security applications.
12
Competent Persons Statement
The information in this report that relates to exploration results including geology interpretation, data
preparation and data quality is based on work compiled by Dr. Stuart Owen who is a Member of the Australian
Institute of Geoscientists. Dr. Owen is a permanent employee of Critica Limited and has sufficient experience
that is relevant to the style of mineralisation and type of deposit under consideration and to the activity which
he is undertaking to qualify as Competent Person as defined in the 2012 Edition of the Australasian Code for
Reporting of Exploration Results, Mineral Resources and Ore Reserves (JORC Code). Dr. Owen consents to the
inclusion in the report of the matters based on his information in the form and context in which they appear.
The information in this announcement that relates to previous exploration results for the Projects is extracted
from the following ASX announcements:
• Jupiter Pilot Optimisation Delivers ~81% Magnet Rare Earth Recovery, with Continued Improvement in
Beneficiation Performance - 14 April 2026
• Critica Appoints DRA Global to Advance Mt Lindsay Scoping Study with ESG-Focused Underground
Approach - 5 May 2026
• Jupiter MREO Advances to ~97% TREO with Strong Recoveries and Improved Magnet REE Performance
- 18 May 2026
• Jupiter and Mt Lindsay Critical Minerals Projects Advance Towards Scoping Study Completion - 17 June
2026
• Jupiter Pilot Plant Delivers ~14x Upgrade to ~3% TREO Concentrate, Reinforcing Low-Cost Beneficiation
Pathway - 27 May 2026
No new Mineral Resource information is contained in this report. Information in this report which refers to
Mineral Resources for the Jupiter Project in Western Australia is taken from the Company’s ASX disclosures dated
11 February 2025, 13 August 2025 and 10 November 2025 at www.critica.limited. The disclosure fairly represents
information compiled by Mr Rodney Brown, a Member of the Australasian Institute of Mining and Metallurgy
and an employee of SRK Consulting (Australia) Pty Ltd, independent of Critica Limited and without conflict of
interest.
The information in this report that relates to Mineral Resources for the Mt Lindsay Projects is based on
information compiled by Dr. Stuart Owen who is a Member of the Australian Institute of Geoscientists. Dr. Owen
is a permanent employee of Critica Limited. Dr Owen has sufficient experience which is relevant to the style of
mineralisation and type of deposits under consideration and to the activity which he is undertaking to qualify as
a Competent Person as defined in the 2004 and 2012 Edition of the ‘Australasian Code for Reporting of
Exploration Results, Mineral Resources and Ore Reserves’. Dr Stuart Owen consents to the inclusion in the report
of the matters based on his information in the form and context in which it appears. This information was
prepared and first disclosed under the JORC Code 2004. It has not been updated since to comply with the JORC
Code 2012 on the basis that the information has not materially changed since it was last reported.
The Company confirms that all material assumptions and technical parameters underpinning the Mineral
Resources Estimates referred to within previous ASX announcements remain current and have not materially
changed since last reported. The Company is not aware of any new information or data that materially affects
the information included in this announcement. The Company confirms that the form and context in which the
Competent Person’s findings are or were presented have not been materially modified.
13
Appendix A: Tenement Register
Mining Tenements Held at End of June 2026 Quarter
Project Location Tenement
Interest at end of June 2026
Quarter
Brothers Western Australia E59/2710 100%
Brothers Western Australia E59/2711 100%
Brothers Western Australia E59/2819 100%
Brothers Western Australia E59/2821 100%
Brothers Western Australia E59/2827 100%
Brothers Western Australia E59/2889 100%
Brothers Western Australia E59/2890 100%
Brothers Western Australia E59/2907 100%
Brothers Wes