Mt Lindsay Investor Webinar Presentation
Released
Released
Announcement PDF
Mt Lindsay Tungsten-Tin Project
September 2026 | ASX: CRI
Scoping Study establishes a pathway towards development
1.0 Mtpa underground development concept | Tasmania, Australia
2
Disclaimer
Authorised by the Board of Critica Limited
This Presentation (Presentation) has been prepared by Critica Limited (CRI or the Company)
and is authorised by the Board of CRI. The information contained in this Presentation is a
professional opinion only. Certain information in this Presentation has been derived from third
parties and though CRI has no reason to believe that it is not accurate, reliable or complete, it
has not been independently audited or verified by CRI.
This Presentation contains general and background information about CRI’s current activities
as at the date of this Presentation and should not be considered to be comprehensive or to
comprise of all the information that an investor should consider when making an investment
decision. CRI is not responsible for providing updated information and assumes no
responsibility to do so. Recipients should conduct their own investigations and perform their
own analysis of the information, statements and opinions contained and this Presentation
should be read in conjunction with CRI’s other periodic and continuous disclosure
announcements lodged with the ASX.
This Presentation is for information purposes only. Neither this nor the information contained in
it constitutes an offer, invitation, solicitation or recommendation in relation to the purchase or
sale of CRI shares in any jurisdiction. This Presentation is not investment advice or a
recommendation to acquire CRI securities and has been prepared without taking into account
the recipient's investment objectives, financial circumstances or particular needs. Recipients
should seek professional advice before deciding if an investment is appropriate.
All securities transactions involve risks, which include (among others) the risk of adverse or
unanticipated market, financial or political developments.
To the fullest extent permitted by law, CRI, its officers, employees, related bodies corporate,
agents and advisers expressly disclaim, to the maximum extent permitted by law, all liabilities
(however caused, including negligence) in respect of, make no representations regarding, and
take no responsibility for, any part of this Presentation and make no representation or warranty
as to the currency, accuracy, reliability or completeness of any information, statements,
opinions, conclusions or representations contained in this Presentation. No responsibility for
any errors or omissions from this arising out of negligence or otherwise is accepted.
Any forward-looking statements and forward-looking information included in this Presentation
involve subjective judgment and analysis and are subject to uncertainties, risks and
contingencies, many of which are outside the control of, and may be unknown to, CRI. In
particular, they speak only as of the date of this Presentation, they assume the success of
CRI’s strategies, and they are subject to significant regulatory, business, competitive and
economic uncertainties and risks. Actual future events may vary materially from the forward-
looking statements and forward-looking information and the assumptions on which they are
based. Recipients of this Presentation are cautioned to not place undue reliance on such
forward-looking statements and forward-looking information.
Basis of Preparation
The Mt Lindsay Scoping Study is a preliminary technical and economic study that is not
sufficient to support the estimation of Ore Reserves or to provide assurance of an economic
development case. No Ore Reserve has been declared. The Scoping Study cautionary
statement, production target basis and funding disclosure are set out in full on the following
page and in the Company’s ASX announcement dated 29 September 2026.
Competent Persons Statements
The information in this presentation that relates to exploration results including geology interpretation,
data preparation and data quality is based on work compiled by Dr. Stuart Owen who is a Member of the
Australian Institute of Geoscientists. Dr. Owen is a permanent employee of Critica Limited and has
sufficient experience that is relevant to the style of mineralisation and type of deposit under
consideration and to the activity which he is undertaking to qualify as Competent Person as defined in
the 2012 Edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and
Ore Reserves (JORC code). Dr. Owen consents to the inclusion in the report of the matters based on his
information in the form and context in which they appear.
The information in this announcement that relates to the Mineral Resource estimates for Mt Lindsay is
based on, and fairly represents, information and supporting documentation prepared by Dr. Stuart
Owen who is a member of the Australian Institute of Geoscientists. The information includes the mining
and metallurgical assumptions used in reporting the Mineral Resource. Dr. Owen has sufficient
experience that is relevant to the style of mineralisation and type of deposit under consideration, and to
the activity he is undertaking, to qualify as a Competent Person as defined in the 2012 Edition of the
JORC Code. Dr Owen consents to the inclusion in the report of the matters based on his information in
the form and context in which they appear.
The information in this announcement that relates to previously reported Exploration Results and
metallurgical test work has been extracted from the Venture Minerals Limited ASX announcements
"Record Breaking Drill Intersection at Mount Lindsay - 147 metres @ 1.0% Tin" dated 16 December 2021
and "Pilot Scale Metallurgy Confirms Excellent Recoveries at Mt Lindsay" dated 31 August 2012. Critica
confirms that it is not aware of any new information or data that materially affects the information
included in those announcements and that the form and context in which the Competent Person's
findings are presented have not been materially modified from those announcements.
The information in this Presentation that relates to the Mt Lindsay Mineral Resource estimate has been
extracted from the Company’s ASX announcement “Critica Updates Mt Lindsay Tin-Tungsten Mineral
Resource to JORC 2012” dated 14 September 2026, and the information relating to the Mt Lindsay
Scoping Study has been extracted from the Company’s ASX announcement dated 29 September 2026.
Critica confirms that it is not aware of any new information or data that materially affects the
information included in those announcements and that all material assumptions and technical
parameters underpinning the estimates and the production target continue to apply and have not
materially changed. Critica confirms that the form and context in which the Competent Person’s
findings have not been materially modified from that announcement.
The Scoping Study technical work, including the underground mine design, mine schedule, processing
flowsheet, infrastructure concept and capital and operating cost estimates, was prepared by DRA
Global.
critica.limited
ASX:
CRI
September
2026
3
Scoping Study Cautionary Statement
Authorised by the Board of Critica Limited
Scoping Study cautionary statement
The Scoping Study referred to in this Presentation has been undertaken to determine the potential
viability of developing the Mt Lindsay Tungsten-Tin Project in north-west Tasmania. It is a
preliminary technical and economic study based on low-level technical and economic assessments
that are not sufficient to support the estimation of Ore Reserves or to provide assurance of an
economic development case at this stage.
Further exploration, evaluation, engineering, metallurgical, environmental, permitting, approvals,
funding, offtake and commercial work is required before Critica will be in a position to assess
whether it is possible to estimate any Ore Reserves or assess whether Critica may be able to provide
any assurance of an economic development case. The Company has concluded that it has a
reasonable basis for disclosing the production target and forecast financial information, based on
the material assumptions, modifying factors and technical information summarised in its ASX
announcement dated 29 September 2026. However, there is no certainty that the assumptions will
be correct or that the outcomes indicated by the Scoping Study will be achieved. Investors should
not make investment decisions based solely on the results of the Scoping Study.
Production target and Mineral Resources
No Ore Reserve has been declared for the Mt Lindsay Project. The Scoping Study production target
is based solely on part of the Main and No.2 deposits within the updated JORC 2012 Mineral
Resource Estimate (refer ASX Announcement “Critica Updates Mt Lindsay Tin-Tungsten Mineral
Resources to JORC 2012”, 14 September 2025. The production target comprises approximately 10.9
Mt of scheduled run-of-mine material, of which approximately 92% is classified as Indicated Mineral
Resources and approximately 8% as Inferred Mineral Resources, after applying mining modifying
factors.
There is a low level of geological confidence associated with Inferred Mineral Resources and there is
no certainty that further exploration work will result in the determination of Indicated Mineral
Resources or that the production target itself will be realised. The Inferred Minerals Resources
underpin approximately 8% of the production target and are predominately scheduled in later years
of the mine plan, with only limited inferred material scheduled in earlier years. The Company has
concluded that the Inferred component is not a determining factor in the viability of the
development scenario and that the Scoping Study does not depend on Inferred Mineral Resources.
Funding
The Scoping Study estimates pre-production capital of approximately A$244.5 million, together with
sustaining capital required over the operating life. Critica has not secured any of the funding required to
develop the Project. The pre-production capital requirement is substantial relative to the Company’s current
market capitalisation and existing financial resources, and the Company would need to obtain substantial
additional external funding to develop the Project.
There are risks that the Company will not be able to raise that amount of funding when needed, or at all. Any
future funding may include one or a combination of debt, equity, strategic partner, offtake-linked, joint
venture, partial sale or other commercial arrangements. If equity funding is required, existing shareholders
may be diluted or their interests may otherwise be affected.
Assumptions and accuracy
The Scoping Study outcomes, production target and forecast financial information are based on the material
assumptions and modifying factors set out in the Company’s ASX announcement dated 29 September 2026,
including mine design, processing, metallurgical recoveries, capital and operating costs, commodity prices,
exchange rates, approvals and funding. Capital and operating cost estimates carry an overall accuracy range
of approximately -25% to +50%.
Base Case processing recoveries of 75% tin, 85% WO₃ and 98% magnetite are modestly above recoveries
demonstrated or estimated in individual historical testwork programs and have not all been demonstrated
simultaneously in a single integrated locked-cycle test program. They remain subject to further metallurgical
validation, variability testing and optimisation.
Given the uncertainties involved, investors should not make investment decisions based solely on the results
of the Scoping Study.
critica.limited
ASX:
CRI
September
2026
4
The Economics Speak for Themselves
Base Case Scoping Study figures prepared by DRA Global; refer ASX announcement 29 September 2026 and read with the cautionary statement and material assumptions in that announcement. NPV at an 8% discount rate; corporate tax
rate 30%. Concentrate payabilities assumed at 94% tin, 80% tungsten and 100% magnetite. Capital and operating cost estimates carry a Scoping Study accuracy range of approximately −25% to +50%. No Ore Reserve has been declared
and there is no certainty the production target or forecast financial information will be realised.
critica.limited
ASX:
CRI
September
2026
KEY SCOPING STUDY METRICS
A$1.42bn
Pre-tax NPV (8%)
A$1.01bn
After-tax NPV (8%)
55.6%
After-tax IRR
~1.9 yrs
Payback
A$3.11bn
LOM EBITDA
A$5.20bn
LOM sales revenue
KEY FINANCIAL ASSUMPTIONS — BASE CASE
Production target basis
1Mt average LOM run-rate
~92% Indicated and ~8% Inferred Mineral
Resources, after mining modifying factors.
Study author
C R I T I C A
A$244.5m
Pre-production capital
4.1x
After-tax NPV / pre-prod capital
Assumption Base Case
Tin price US$45,000/t
Tungsten APT price US$2,500/mtu
Magnetite concentrate (65% Fe) US$115/dmt
Exchange rate (AUD:USD) 0.65
Discount rate 8%
Corporate tax rate 30%
Mt Lindsay is one of the largest undeveloped tungsten–tin assets in a tier 1 jurisdiction
A$2.67bn
Pre-tax LOM free cash flow
A$1.92bn
After-tax LOM free cash flow
US$314/mtu
Indicative tungsten operating cost*
*After tin and magnetite by-product credits;
derived non-IFRS measure, not C1 or AISC.
5
Why the West needs Mt Lindsay Tungsten and Tin
critica.limited
ASX:
CRI
September
2026
Tungsten: carbide tooling and advanced
manufacturing
Tin: solder for electronics and data centres
C R I T I C A
53% OF TIN DEMAND: SOLDER
Tin solder underpins electronics, AI
infrastructure and data centres.
TUNGSTEN: INDUSTRIAL NECESSITY
Carbide tooling supports advanced
manufacturing; defence adds strategic
demand.
NON-CHINESE SUPPLY TAKES TIME
New mines and refining require investment,
permits and years to deliver.
16kt EX-CHINA SUPPLY GAP
Forecast primary tungsten gap in 2030, even
if announced projects deliver.*
36% OF TIN SUPPLY EXPOSED
Estimated share of 2025 tin concentrate
supply facing jurisdictional risk.
79% MINING / 85% REFINING
China’s estimated share of tungsten mine
output and APT refining capacity.
*S&P Global Energy, Tungsten Market Report (Aug 2026); Project Blue/USGS. Tin supply: International Tin Association (2026). Figures are third-party
market estimates.
TUNGSTEN TIN
TUNGSTEN
TIN
Concentrated supply | Slow supply response | Critical industrial demand | Few practical substitutes
6
critica.limited
ASX:
CRI
September
2026
Concentrated Supply Is Driving a Structural Repricing
TUNGSTEN APT
US$2,500/mtu
SEPTEMBER BENCHMARK
US$3,000/mtu
~17% BELOW REFERENCED BENCHMARK
Concentrated mining and refining; strategic interest in secure,
non-Chinese supply.
Asian Metal European APT benchmark, 1 Sep 2026
TIN
SCOPING STUDY BASE CASE
US$45,000/t
SEPTEMBER BENCHMARK
US$54,725/t
~18% BELOW REFERENCED BENCHMARK
Electronics and electrification demand alongside constrained,
exposed supply.
LME cash settlement, 1 Sep 2026
The assumptions are long-term assessment prices - not an extrapolation of current spot prices.
They reflect Critica’s view that structural supply constraints and strategic demand support longer-term pricing.
Source: Mt Lindsay Scoping Study, Commodity Price Assumptions. Mt Lindsay produces scheelite and tin concentrates; modelled revenue applies 80% tungsten and 94% tin payabilities, plus transport and selling
costs. Benchmarks are dated market references, not forecasts.
SCOPING STUDY BASE CASE
Base Case prices below September 2026 benchmarks, reflecting enduring supply constraints
C R I T I C A
7
A Credible Development Pathway
critica.limited
ASX:
CRI
September
2026
Distance to the Port of Burnie per the Mt Lindsay Scoping Study (ASX announcement 29 September 2026). Tasmania’s electricity generation is predominantly hydroelectric; the Scoping Study assumes grid power as the primary electricity
supply, with connection capacity and commercial terms subject to confirmation. Named nearby operations are third-party mines cited for regional context only
100% ownership and granted Mining
Lease
Established project ownership and mining
tenure
Established Mineral Resource
More than 88,000m of diamond drilling
and extensive technical work
Established mining district
Located near operating mines and
established mining services
Existing infrastructure and access
Road access, nearby power infrastructure
and regional rail
Established export infrastructure
Port of Burnie approximately 120 km by
road
◈
100%
Ownership and granted Mining
Lease
88,000m
Diamond drilling completed
Hydro
Predominantly renewable
Tasmanian grid
120km
By road to Port of Burnie
Key foundations already in place to advance Mt Lindsay towards a DFS
~ 120km
C R I T I C A
8
An Established Resource Underpins Development
critica.limited
ASX:
CRI
September
2026
C R I T I C A
PLAN VIEW OF THE MAIN AND NO.2 MINERALISED SYSTEMS
14.3 Mt ~32 kt
~23 kt ~92%
Main and No. 2
Mineral Resource
Production target
from Indicated
Mineral Resources
Contained WO₃
Contained tin
Supported by more than 88,000 m of
diamond drilling
Additional Mineral Resources lie outside the current Scoping Study focus, providing
opportunities for further evaluation
The Main and No. 2 deposits represent 75% of Mt Lindsay’s total Mineral Resource
9
A Defined Underground Mining Concept
*Conceptual arrangement of the Mt Lindsay underground development showing the Main Skarn and No. 2 Skarn mineralised systems beneath surface, underground access from the existing HEC Quarry area, and the relationship to the
proposed conveyor, processing plant, tailings storage and existing infrastructure. The concept illustrates how underground mine access and surface infrastructure are being considered together to maximise the use of existing disturbed
areas and minimise new surface disturbance. Final locations and configurations remain subject to further engineering, environmental assessment and regulatory approvals. Refer ASX announcement 29 September 2026.
Defined underground access
Proposed decline from a portal within
the existing HEC quarry
Integrated site layout
Underground conveyor connecting the
mine to the proposed processing
plant, approximately 600 m from the
portal
Designed Around Existing
Disturbance
Proposed infrastructure designed
around existing disturbed areas, with
potential underground tailings backfill.
critica.limited
ASX:
CRI
September
2026
C R I T I C A
1.0 Mtpa
Proposed mining rate
13.5 years
Mining schedule
11.6 years
Processing life
10.9 Mt
Material processed
A 1.0 Mtpa low-impact underground operation leveraging existing infrastructure
10
Underground Access from an Existing Quarry
ILLUSTRATIVE TWIN-DECLINE PORTAL ARRANGEMENT
EXISTING HEC QUARRY AREA PROPOSED FOR THE PORTAL
Final portal location and configuration remain subject to further engineering, environmental assessment and regulatory approvals.
critica.limited
ASX:
CRI
September
2026
C R I T I C A
A fundamentally different development concept designed to reduce surface disturbance and integrate mine,
infrastructure and processing from the outset.
The portal sits inside historical HEC Quarry disturbance, ~600m from the plant site
Processing Flowsheet
C R I T I C A
Simplified from the Study's proposed processing flowsheet. The final process configuration, recovery assumptions and concentrate specifications remain subject to further metallurgical validation and engineering. Base Case processing
recoveries have not all been demonstrated simultaneously in a single integrated locked-cycle test program.
11
critica.limited
ASX:
CRI
September
2026
19.3kt
Scheelite concentrate (WO₃)
Recovery 85%
TUNGSTEN
31.6kt
Tin concentrate (Sn)
Recovery 75%
TIN
2.14Mt
Magnetite concentrate (Fe)
Recovery 98%
MAGNETITE
Three saleable concentrate streams
A conventional flowsheet producing three concentrates: tin, tungsten and magnetite
A$244.5m to Production | 4.1x Capital Value
C R I T I C A
A$244.5m
Pre-production capital
A$197.3m
Sustaining capital + closure
A$441.8m
Total LOM capital
4.1x
After-tax NPV / pre-prod capital
Capital estimates from the Mt Lindsay Scoping Study (DRA Global), at Scoping Study accuracy of approximately −25% to +50%. Excludes working capital and financing costs. Refer ASX announcement 29 September 2026.
12
critica.limited
ASX:
CRI
September
2026
PRE-PRODUCTION CAPITAL TOTAL LIFE-OF-MINE CAPITAL
A$244.5m A$441.8m
Mine development A$122.0m
Processing &
infrastructure
A$94.0m
Contingency A$28.5m
Pre-production A$244.5m
Sustaining capital A$177.3m
Mine closure A$20.0m
Defined capital requirements with an after-tax NPV of 4.1 times pre-production investment
13
Sensitivities show the independent effect of ±20% changes in each variable, with all other assumptions held constant. Base Case after-tax NPV₈: A$1,006m. Proposed mitigation activities are forward-looking and do not eliminate risk.
Scoping Study accuracy approximately −25% to +50%; refer ASX announcement 29 September 2026. No Ore Reserve has been declared.
critica.limited
ASX:
CRI
September
2026
C R I T I C A
Strong Project Economics Across Key Sensitivities
AFTER-TAX NPV₈ SENSITIVITY | ±20% CHANGE
600 800 1000 1200 1400
BASE A$1,006m
Commodity price 614 1399
Ore grade 625 1388
Operating costs 855 1157
Mining costs 905 1107
Upfront capex 975 1037
Processing costs 976 1036
Waste tonnes 988 1025
Sustaining capex 989 1023
After-tax NPV₈ (A$m)
COMMODITY PRICES
A$614m–A$1,399m
Base Case prices are below September 2026 benchmarks;
supply concentration supports the Company’s long-term pricing
view.
ORE GRADE
A$625m–A$1,388m
More than 88km of drilling completed. Further resource
definition and mine-plan optimisation are planned to improve
grade confidence.
OPERATING & MINING COSTS
Secondary NPV drivers
Further engineering, contractor pricing and mine-design work
will refine Scoping Study cost estimates.
Commodity prices and ore grade have the greatest impact on NPV; further technical work will focus on the key project assumptions.
A$1.0bn Base Case NPV with prudent pricing and focused risk management
From Scoping Study to First Production
2026
H1 H2
2027
H1 H2
2028
H1 H2
2029
H1 H2
Scoping Study Definitive Feasibility Study (18 months)
Environmental Assessment and Permitting (parallel)
Construction, Commissioning and Ramp-up
Final Investment
Decision (FID)
mid-2028
First Production
end 2029
1 Definitive Feasibility Study
H2 2026 – H1 2028
• Optimise design, costs and schedule
• Advance offtake and financing discussions
• Refine environmental and social studies
2 Progress permitting
2026 – 2028 (parallel)
• Environmental impact assessment
• Progress key approvals
• Stakeholder and community engagement
3 Final Investment Decision
Mid-2028
• Subject to DFS outcomes, approvals and
funding
• Enables commencement of construction
4 Construction and ramp-up
H2 2028 – 2029
• Indicative construction period
• Commissioning and operational readiness
• First production targeted end 2029
Indicative development pathway only. Timing is subject to further studies, engineering, environmental and regulatory approvals, product qualification, commercial outcomes, funding and a future Board decision to proceed. Refer to Mt Lindsay Scoping Study
announcement, 29 September 2026.
A defined development pathway targeting first production by end-2029
C R I T I C A
14
critica.limited
ASX:
CRI
September
2026
15
A Team That Can Deliver
critica.limited
ASX:
CRI
September
2026
C R I T I C A
Deep mining, exploration, metallurgy and capital markets experience
MANAGEMENT
Jacob Deysel | CEO
Nearly 30 years in global mining and critical minerals • Goldfields · Rio Tinto · Kenmare · UEC
Dr. Stuart Owen | Exploration Manager
25+ years global exploration experience • Led Paulsens gold and Jupiter REE discovery
Dr. Natalee Bonnici | Senior Exploration Geologist
15+ years in geology and geometallurgy • Triumph VHMS discovery; resource delivery
Dr. Thi Thu Hien Dinh | Chief Metallurgist
23+ years in rare earths and battery metals • Led REE, lithium and nickel processing teams
BOARD
Tim Lindley | Non-Executive Chairman
30+ years in global investment banking • Equity raising, project finance and M&A
Nick Cernotta | Non-Executive Director
40+ years global mining engineering and leadership • Fortescue · Barrick · Macmahon
Discovery to development,
backed by capital markets
expertise
MINING & DEVELOPMENT
Global operating and project development
experience
DISCOVERY & METALLURGY
Jupiter REE discovery and specialist processing
expertise
CAPITAL & GOVERNANCE
Project finance, equity markets and disciplined
execution
1. As previously announced, Jamie Byrde will be departing Critica. The appointment of an incoming CFO will be confirmed in due course.
2. Management and Board experience as presented in Critica’s September 2026 investor materials.
20+ years in ASX-listed companies • Strong focus on capital discipline, governance and funding
Jamie Byrde | CFO & Executive Director1
16
Corporate Snapshot
critica.limited
ASX:
CRI
September
2026
C R I T I C A September 2026
Australian critical minerals portfolio | Mt Lindsay and Jupiter
COMPANY AT A GLANCE
ASX ticker CRI
Listed since 2006
Portfolio Mt Lindsay tungsten–tin | Tasmania
Jupiter rare earths | Western Australia
Jurisdiction 100% owned Australian portfolio
FINANCIAL SNAPSHOT
3.03bn
Shares on issue
A$0.024
Last price¹
A$72.7m
Market cap¹
A$5.3m
Cash²
Nil
Debt
A$67.4m
Enterprise value¹
SHAREHOLDER BREAKDOWN SHARE PRICE PERFORMANCE
¹ Share price, market capitalisation and enterprise value: 28 September 2026. ² Cash: 30 June 2026.
Source: Critica corporate snapshot supplied for redesign. Financial figures are historical, not current market quotes.
22.41%
Top 20
Shareholders
17
critica.limited
ASX:
CRI
September
2026
C R I T I C A
The Scoping Study Is the Catalyst
A$1.01bn
After-tax NPV₈
4.1x
NPV / pre-production capital
A$244.5m
Pre-production capital
01 Feasibility & resource
Advance the DFS
Refine engineering, mine design, metallurgy and resource
confidence ahead of a potential investment decision.
02 Offtake & strategic partners
Progress commercial engagement
Use the study outcomes to advance tungsten and tin customer
discussions and product qualification.
03 Funding & approvals
Build development readiness
Progress environmental assessment, permitting and funding
discussions alongside the DFS.
04 Clear development pathway
Target first production end-2029
Indicative mid-2028 FID, followed by construction, commissioning
and ramp-up, subject to key conditions.
The Scoping Study marks the start of the next development phase—not the end of the investment case.
Indicative pathway only. Economics are Scoping Study estimates and subject to uncertainty. Development timing depends on further studies, approvals, financing, commercial outcomes and a future Board decision. Refer to
the Mt Lindsay Scoping Study ASX announcement dated 29 September 2026.
Compelling economics provide the platform to advance feasibility, offtake and project funding
18
Why Own Critica Now?
critica.limited
ASX:
CRI
September
2026
C R I T I C A
A$244.5m
MT LINDSAY | SCOPING STUDY DELIVERED
A$1.01bn
After-tax NPV₈
4.1x
NPV / pre-production capital Pre-production capital
NOW
Mt Lindsay: Unlocking the next
phase
Advance the DFS and resource confidence
Progress tungsten and tin offtake discussions
Build strategic partnerships, funding and approvals
NEXT
Jupiter: The next study catalyst
Forthcoming Scoping Study
Potential to demonstrate further portfolio value
Adds another development opportunity to the platform
ONE CRITICAL MINERALS PLATFORM • TWO MAJOR PROJECTS • MULTIPLE POTENTIAL CATALYSTS
Scoping Study estimates are preliminary and subject to uncertainty. Mt Lindsay development remains subject to further studies, approvals, financing and a future Board decision. Jupiter Scoping Study outcomes
and timing remain subject to completion and announcement.
Mt Lindsay establishes the economic foundation. Jupiter offers the next major catalyst
A$244.5m
Contact
ASX: CRI
Address: Level 2, 16 Altona Street, West Perth WA 6005
Website: critica.limited
Follow Us
linkedin.com/company/criticaltd
@Critica_CRI
Investor Relations
Dannika Warburton
Investability
investors@investability.com.au
Critica CEO
Jacob Deysel
Phone: +61 8 6279 9428
Email: info@critica.limited