Critica Advances Mt Lindsay Tin-Tungsten Underground Project
Released
Released
Announcement PDF
ASX Announcement
18 August 2026 | ASX: CRI
CRITICA LIMITED
Level 2, 16 Altona Street,
West Perth, Western
Australia ABN 51 119 678 385
T: +61 8 6279 9428
E: admin@critica.limited
critica.limited
Unlocking Value at the Mt Lindsay Tin-Tungsten Project
Through Underground Development
The Mt Lindsay Scoping Study is taking a fresh, first-principles approach to evaluate how one of Australia’s
largest undeveloped tin-tungsten resources can be developed in a strengthening commodity market while
meeting today’s mining, environmental and commercial expectations.
Critica Limited (ASX: CRI) (“Critica” or “the Company”) is pleased to provide an update on the Scoping
Study underway for its wholly owned Mt Lindsay Tin-Tungsten Project in north-west Tasmania. Mt Lindsay
forms a key part of Critica’s growing Australian critical minerals platform, complementing the Company’s
Jupiter rare earths, yttrium and gallium project in Western Australia.
Mt Lindsay is being reassessed at a time when tin and tungsten markets have strengthened materially, with
tungsten becoming increasingly strategic as global supply-chain security gains importance. This provides
Critica with a significant opportunity to advance a project capable of diversifying the supply of two critical
minerals into high-demand markets within an attractive pricing environment.
Highlights
• Tungsten and tin markets have strengthened materially, underpinned by
growing strategic demand and secure supply-chain requirements.
• Mt Lindsay is well positioned in the current critical-minerals and commodity
environment as a significant undeveloped tin-tungsten resource.
• Additional by-product potential being evaluated, including copper, boron,
fluorspar and other minerals.
• Innovative underground mining beneath Mt Lindsay mitigating historical
open-pit concept, tangibly and substantially reducing surface disturbance.
• Mine access, infrastructure and materials handling being optimised as one
integrated project design, leveraging access to hydroelectric power and
opportunities for lower-emission electrification.
• Underground backfill being evaluated to reduce permanent surface tailings
storage and support mining.
• Existing disturbed areas and infrastructure prioritised to minimise new
surface disturbance.
• Potential to deliver meaningful economic benefits for Tasmania, including
investment and employment as the Project advances.
• DRA Global leading the Mt Lindsay Underground Mining Scoping Study,
targeted for completion in Q3 2026.
• Mt Lindsay represents one of two Scoping Studies targeted by Critica for Q3
2026, alongside the Jupiter critical minerals project in Western Australia.
2
The strength of the current market is reflected in recent benchmark pricing, with ammonium paratungstate
(APT) quoted at US$3,075/mtu CIF Rotterdam on 6 August 2026¹ and LME tin cash settlement at US$56,050
per tonne on 12 August 2026.²
Against this backdrop, Critica has approached the current Scoping Study from first principles, asking how
Mt Lindsay should be developed for today’s commodity markets, mining methods and environmental
expectations. Rather than simply updating previous development studies, the Scoping Study is evaluating
a fundamentally different underground development concept, integrating mine design, infrastructure,
processing and environmental considerations from the outset.
Critica’s CEO Jacob Deysel commented:
“Mt Lindsay has long been recognised as one of Australia’s largest undeveloped tin-tungsten resources.
The resource hasn’t changed — but the world around it has. Tin and tungsten markets have strengthened
materially, tungsten has become increasingly strategic to global technology, manufacturing and defence
supply chains, and the importance of secure and diversified supply has never been clearer.
This changing market provides a compelling backdrop to reassess Mt Lindsay. At the same time,
expectations around how major mining projects should be developed have evolved. We have the
opportunity to step back, challenge historical assumptions and build the right project for today’s world -
not simply update yesterday’s design.
In my experience, the most important decisions in a mining project are made long before the first tonne of
ore is mined. Those early decisions influence everything that follows — from the mining method and
project footprint to infrastructure, capital efficiency, permitting and ultimately the long-term success of
the project.
That thinking has shaped our approach to the current Scoping Study. We’ve gone back to first principles,
evaluating every major component as part of an integrated development concept. Our objective is to build
a better Mt Lindsay — one that is technically robust, commercially compelling and designed responsibly
from the outset.
We are excited by the opportunity to advance such a strategic Australian asset, with the potential to
diversify the supply of two essential minerals that are becoming increasingly important to global
technology, manufacturing and defence supply chains, while creating the potential for meaningful
investment, employment and economic benefits for Tasmania.”
¹ Source: Shanghai Metals Market (SMM), APT CIF Rotterdam, 6 August 2026.
² Source: Westmetall, LME Tin Cash Settlement Price, 12 August 2026.
3
Figure 1: Mt Lindsay Project Location, North-West Tasmania
Figure 1: Location of Critica’s wholly owned Mt Lindsay Tin-Tungsten Project in north-west Tasmania. The Project is
situated within an established mining region with access to existing road and electricity infrastructure.
A Fresh Approach to Mt Lindsay
Mt Lindsay is a significant tin-tungsten mineral system located within an established mining region in
western Tasmania. The broader mineral system also contains additional mineral potential, including
copper, boron, fluorspar and other minerals, which is being considered as part of the broader evaluation of
the Project.
The Project has been extensively explored and studied over many years. Rather than simply updating
previous development concepts, Critica has used the current Scoping Study as an opportunity to step back
and reset how Mt Lindsay should be developed, applying a first-principles approach to every major aspect
of the Project.
The objective is to build the best project possible by integrating mining, infrastructure, processing,
environmental and commercial considerations from the outset, recognising that the decisions made early
in project design have the greatest influence on long-term technical, environmental and commercial
outcomes.
This philosophy is guiding every aspect of the Scoping Study, through a clear design hierarchy:
• Avoid new disturbance where practical
• Maximise the use of existing disturbed areas and infrastructure corridors
• Integrate mining and surface infrastructure to minimise the overall project footprint
• Reduce long-term environmental disturbance through responsible project design
The following sections outline how this philosophy is being applied across each major component of the
Scoping Study.
4
Underground Access – Making Use of Existing Disturbance
One of the earliest and most important design decisions in an underground mining project is the location
of any surface expression such as the primary mine access / portal.
Consistent with Critica’s first-principles approach, the Scoping Study is evaluating portal access within an
area that has already been extensively disturbed by historical stone quarrying, providing the opportunity to
establish the principal mine entry while minimising the need for new surface disturbance.
Existing roads and infrastructure corridors are also being utilised wherever practical. From the portal,
underground development would provide access to the Mt Lindsay mineralised system while allowing the
majority of mining activities to remain below surface.
This represents an important departure from the historical open-pit development concept. By making use
of existing disturbance from the outset, the underground access strategy establishes the foundation for a
more integrated project layout while supporting Critica’s objective of reducing the overall surface footprint
of the proposed development.
Figure 2: Proposed Underground Portal and Surface Infrastructure Areas
Figure 2: Existing disturbed areas being considered for the Mt Lindsay underground portal and associated surface
infrastructure. The proposed portal is located within the existing historical HEC Quarry disturbance, approximately 600
m from the potential plant site. The potential plant area is also located close to existing infrastructure, including the
sealed Pieman Road and electricity transmission lines. These locations are being evaluated as part of the Scoping
Study’s objective to maximise the use of existing disturbance and infrastructure while minimising the requirement for
new surface disturbance.
5
Figure 3: Existing HEC Quarry and Conceptual Underground Portal Arrangement
Figure 3: Existing HEC Quarry area proposed for the Mt Lindsay underground mine portal (left), together with an
illustrative underground portal arrangement (right). Locating the principal mine access within the existing quarry
disturbance is being evaluated as part of the Scoping Study, with the objective of reducing the requirement for new
surface disturbance. Final portal location and configuration remain subject to ongoing engineering, environmental
assessment and regulatory approvals.
Underground Mining at the Core of the Project
The underground development strategy allows Critica to evaluate access to the Mt Lindsay mineralised
system beneath Mt Lindsay, with proposed mining operations located underground rather than through
surface excavation of the mountain. This substantially reduces the extent of surface disturbance required
compared with the historical open-pit development concept.
The current Scoping Study is evaluating underground development, stope optimisation, mine scheduling
and the appropriate development scale across the Main Skarn and No. 2 Skarn mineralised systems. This
work isbeingundertakenas part ofan integrated assessment of minedesign, operating strategy and project
economics.
Previous studies identified long-hole open stoping with backfill. The current programme is reassessing the
mine design, sequencing and production schedule using updated engineering assumptions and the new
Mineral Resource Estimate.
Importantly, the objective is not to maximise tonnes or mine life in isolation. The Scoping Study is assessing
the development configuration that delivers the strongest overall project outcome, balancing mine
economics, capital requirements, operational efficiency, mine life and the long-term project footprint.
Integrated Surface Infrastructure
With the underground mining concept established, the Scoping Study is now optimising the location and
configuration of surface infrastructure as part of a single integrated project layout.
Rather than adapting historical infrastructure locations, the Scoping Study is evaluating the placement of
the processing plant, mine services and associated infrastructure, low carbon emission materials handling
systems, water management infrastructure and supporting facilities as an integrated operating system
centred around the underground mine.
Existing roads and disturbed infrastructure corridors are being utilised wherever practical, while alternative
materials handling solutions, including conveyors, are also being evaluated to improve operating
efficiency, reduce truck movements and minimise the requirement for additional road construction and
6
surface disturbance. The Project’s access to established hydroelectric power infrastructure also provides
an opportunity to evaluate electrification and other lower-emission options for underground materials
handling as the Project design advances.
By integrating the underground mine with surface infrastructure from the outset, the Scoping Study aims to
create a compact, efficient and operationally effective project layout while minimising unnecessary
duplication of infrastructure.
Figure 4: Integrated Surface Infrastructure Layout
Figure 4: Conceptual surface infrastructure layout currently being evaluated as part of the Mt Lindsay Scoping Study.
The design integrates underground access, processing infrastructure and materials handling while maximising the use
of existing disturbance wherever practical. Final mine design remains subject to the updated Mineral Resource
Estimate and ongoing optimisation studies.
Figure 5: Conceptual Underground Development and Surface Infrastructure Arrangement
Figure5:Conceptualarrangementofthe MtLindsayundergrounddevelopmentshowingthe MainSkarnandNo.2 Skarn
mineralised systems beneath surface, underground access from the existing HEC Quarry area, and the relationship to
the proposed conveyor, processing plant, tailings storage and existing infrastructure. The concept illustrates how
underground mine access and surface infrastructure are being considered together to maximise the use of existing
disturbed areas and minimise new surface disturbance. Final locations and configurations remain subject to ongoing
Scoping Study engineering, environmental assessment and regulatory approvals.
7
Integrated Tailings and Backfill Strategy
The Scoping Study is evaluating underground backfill as an integral part of the Mt Lindsay development
concept, linking the mining method with the overall approach to tailings management.
The concept being assessed provides for a portion of process tailings to be returned underground as
backfill, potentially reducing the volume of tailings requiring permanent surface storage while also
supporting the underground mining sequence. Surface tailings storage would continue to form part of the
overall tailings-management strategy for material not utilised as backfill.
The final balance between underground backfill and surface tailings storage will depend on mine
scheduling, tailings characteristics, backfill requirements and the outcomes of ongoing engineering and
testwork.
By considering mine design, backfill and tailings management as an integrated system from the outset,
Critica is seeking to reduce the long-term surface footprint associated with tailings storage while
supporting an efficient underground mining operation.
Responsible Development by Design
The Mt Lindsay Scoping Study provides Critica with the opportunity to integrate technical, environmental
and social considerations into the Project from the outset. The Company believes the decisions made
during project design have the greatest influence on long-term project outcomes.
Mine access, infrastructure, materials handling, water management and tailings are therefore being
evaluated as a single integrated development concept.
Critica’s objective is to develop a project that is technically robust, commercially attractive and founded
on responsible development principles. Any future development of Mt Lindsay will remain subject to
detailed environmental studies, stakeholder engagement and regulatory approvals.
DRA Global Advancing the Scoping Study
Critica appointed DRA Global in May 2026 to lead the Mt Lindsay Underground Mining Scoping Study.
DRA is progressing the integrated engineering workstreams required to evaluate the underground
development concept, including mine design, infrastructure, processing, materials handling, tailings
management and project optimisation.
The Scoping Study is being undertaken in parallel with an updated Mineral Resource Estimate, allowing the
resource model, mine design, processing assumptions and project infrastructure to be developed as a
single integrated project concept.
This coordinated approach provides the foundation for evaluating the technical, operational and economic
performance of the new Mt Lindsay development strategy.
Building a Better Mt Lindsay
Mt Lindsay is being evaluated on a fundamentally different development basis from previous studies.
Rather than updating yesterday’s project, Critica is applying first-principles thinking to build the best Mt
Lindsay possible for today’s operating, commodity and critical-minerals environment.
The combination of a significant established tin-tungsten resource, strengthening commodity markets and
the increasing strategic importance of secure tin and tungsten supply provides a compelling backdrop for
the Project’s reassessment.
8
The Scoping Study will determine how the new underground development concept translates into
technical, commercial and environmental outcomes, while continuing to identify opportunities to enhance
the Project’s long-term value and reduce its overall development footprint.
Next Steps
• Updated Mineral Resource Estimate: Critica is progressing the updated Mt Lindsay Mineral
Resource Estimate, which will provide the basis for final underground mine optimisation and
scheduling.
• Scoping Study: DRA Global will continue advancing the integrated Scoping Study workstreams,
including mine design, processing, infrastructure, materials handling, tailings and development
optimisation.
• Study completion: Critica remains on track to complete the Mt Lindsay Underground Mining
Scoping Study during Q3 2026.
Advancing Critica’s Critical Minerals Platform
Critica is advancing parallel Scoping Studies across its two key critical minerals projects. The progress
below highlights the work completed and key milestones underway at Jupiter and Mt Lindsay, with both
Scoping Studies targeted for completion in Q3 2026.
Authorised by the Board of Critica Limited.
9
Jacob Deysel
CEO
Critica Limited
Level 2, 16 Altona Street, West Perth, Western Australia
T: + 61 8 6279 9428 | admin@critica.limited | critica.limited
Investor and Media Relations
Dannika Warburton
InvestabilityPartners
investors@investability.com.au
JOIN CRITICA’S INTERACTIVE INVESTOR HUB
Sign up and engage with our investor relations team
BUILDING A CRITICAL MINERALS PLATFORM
RARE EARTHS | YTTRIUM | GALLIUM | TIN | TUNGSTEN
Critica Limited (ASX: CRI) is advancing a
portfolio of critical minerals projects with
exposure to commodities used in defence,
semiconductors, artificial intelligence,
advanced manufacturing and
electrification.
The Jupiter Project in Western Australia
provides exposure to rare earths, yttrium
and gallium, while the Mt Lindsay Project in
Tasmania provides exposure to tin and
tungsten.
Together, these projects provide exposure
to minerals essential to future industrial
growth and national security applications.
10
Competent Persons Statement
The information in this report that relates to exploration results including geology interpretation, data
preparation and data quality is based on work compiled by Dr. Stuart Owen who is a Member of the
Australian Institute of Geoscientists. Dr. Owen is a permanent employee of Critica Limited and has
sufficient experience that is relevant to the style of mineralisation and type of deposit under consideration
and to the activity which he is undertaking to qualify as Competent Person as defined in the 2012 Edition
of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (JORC
code). Dr. Owen consents to the inclusion in the report of the matters based on his information in the form
and context in which they appear.
No new Mineral Resource information is contained in this report.
All material assumptions and technical parameters underpinning the Minerals Resource Estimates
referred to within previous ASX announcements continue to apply and have not materially changed since
last reported. The Company is not aware of any new information or data that materially affects the
information included in this announcement.
Forward Looking Statements
This ASX announcement contains certain statements that may constitute a “forward looking statement”.
Such statements are only predictions and are subject to inherent risks and uncertainties, which could
cause actual values, results, or performance achievements to differ materially from those expressed,
implied or projected in any forward looking statements.
Forward looking statements are statements that are not historical facts. Words such as “expect(s)”,
“feel(s)”,“believe(s)”,“will”,“may”,“anticipate(s)”and similar expressions are intended to identify forward-
looking statements. These statements include, but are not limited to statements regarding future
production, resources or reserves and exploration results. All such statements are subject to certain risks
and uncertainties, many of which are difficult to predict and generally beyond the control of the Company,
that could cause actual results to differ materially from those expressed in, or implied or projected by, the
forward-looking information and statements.
These risks and uncertainties include, but are not limited to: (i) those relating to the interpretation of drill
results, the geology, grade and continuity of mineral deposits and conclusions of economic evaluations,
(ii) risks relating to possible variations in reserves, grade, planned mining dilution and ore loss, or recovery
rates and changes in project parameters as plans continue to be refined, (iii) the potential for delays in
exploration or development activities or the completion of feasibility studies, (iv) risks related to
commodity price and foreign exchange rate fluctuations, (v) risks related to failure to obtain adequate
financing on a timely basis and on acceptable terms or delays in obtaining governmental approvals or in
the completion of development or construction activities, and (vi) other risks and uncertainties related to
the Company’s prospects, properties and business strategy. Our audience is cautioned not to place undue
reliance on these forward-looking statements that speak only as of the date hereof, and we do not
undertake any obligation to revise and disseminate forward-looking statements to reflect events or
circumstances after the date hereof, or to reflect the occurrence of or non-occurrence of any events.
The Company believes that it has a reasonable basis for making the forward-looking Statements in the
announcement based on the information contained in this and previous ASX announcements.
Share your feedback