Mt Lindsay Study Delivers Strong Tungsten and Tin Economics
Released
Released
Announcement PDF
ASX Announcement
29 September 2026 | ASX: CRI
CRITICA LIMITED
Level 2, 16 Altona Street,
West Perth, Western
Australia ABN 51 119 678 385
T: +61 8 6279 9428
E: admin@critica.limited
critica.limited
Mt Lindsay Scoping Study Delivers Strong Economics
to Advance Underground Tungsten-Tin Development
Critica Limited (ASX: CRI) (“Critica” or “the Company”) is pleased to announce the outcomes of the
Scoping Study for its 100%-owned Mt Lindsay Tin-Tungsten Project in north-west Tasmania, evaluating a
1.0 Mtpa underground mining and processing development.
The Scoping Study outlines an underground development pathway for Mt Lindsay with significant
exposure to tin and tungsten, commodities with important applications across electronics, advanced
manufacturing, defence and aerospace.
The Study, prepared by DRA Global, evaluates an owner-operated underground mining and processing
operation incorporating dual-decline access, longhole open stoping with paste fill, conveyor material
handling, a tin-tungsten-magnetite processing flowsheet and supporting infrastructure. The underground
concept represents a material departure from the historical open-pit development approach and seeks to
minimise additional surface disturbance through project design.
Cautionary statement
The Scoping Study referred to in this announcement has been undertaken to determine the potential
viability of developing the Mt Lindsay Tin-Tungsten Project in north-west Tasmania. The Scoping Study is a
preliminary technical and economic study based on low-level technical and economic assessments that
are not sufficient to support the estimation of Ore Reserves or to provide assurance of an economic
development case at this stage. Further evaluation work and appropriate studies are required before Critica
will be in a position to estimate any Ore Reserves or assess whether Critica may be able to provide any
assurance of an economic development case.
The Scoping Study production target is based solely on part of the Main and No.2 deposits within the
updated JORC 2012 Mineral Resource Estimate (refer ASX announcement “Critica Updates Mt Lindsay Tin-
Tungsten Mineral Resource to JORC 2012”, 14 September 2026). The production target comprises
approximately 10.9 Mt of scheduled run-of-mine material after applying mining modifying factors, of which
approximately 92% is derived from Indicated Mineral Resources and approximately 8% from Inferred
Mineral Resources.
There is a low level of geological confidence associated with Inferred Mineral Resources and there is no
certainty that further exploration work will result in the determination of Indicated Mineral Resources or that
the production target itself will be realised. The Inferred Mineral Resources underpin approximately 8% of
the production target and are predominantly scheduled in the later years of the mine plan, with only limited
Inferred material scheduled in earlier years. Critica has concluded that the Inferred Mineral Resources are
not a determining factor in the viability of the development scenario.
2
Critica CEO, Jacob Deysel, commented:
“The Mt Lindsay Scoping Study represents an important step forward for Critica and a fundamental
rethink of how this significant tin-tungsten resource could be developed. By moving from the historical
open-pit concept to an underground development pathway, we have outlined a project with a smaller
surface footprint and strong Scoping Study-level modelled economics. The Project also benefits from its
location within an established Tasmanian mining region, with existing road access, proximity to
established hydroelectric power infrastructure and access to export infrastructure at Burnie.
The Base Case generates a pre-tax NPV of approximately A$1.42 billion, a pre-tax IRR of
approximately 65% and an after-tax payback period of approximately 1.9 years, against pre-
production capital of approximately A$244.5 million.
Mt Lindsay also gives Critica substantial exposure to tungsten, which contributes approximately 75% of
modelled Base Case life-of-mine revenue, at a time when secure Western supply of this critical mineral is
becoming increasingly strategically important. Importantly, the current Scoping Study economics exclude
copper and other potential by-products, which provide potential upside subject to further metallurgical
and commercial evaluation.
Our focus now is on systematically advancing the technical, metallurgical, approvals, funding and
commercial work required to progress Mt Lindsay toward a Definitive Feasibility Study (DFS).”
The Scoping Study outcomes, production target and forecast financial information are based on the
material assumptions and modifying factors outlined in this announcement, including mine design,
processing, metallurgical recoveries, capital and operating costs, commodity prices, exchange rates,
approvals and funding. The Scoping Study has allowed for an overall accuracy range of approximately -25%
to +50%. Critica considers that it has reasonable grounds for the production target and forecast financial
information on the basis of those assumptions and modifying factors. However, there is no certainty that
the assumptions will prove to be correct or that the outcomes indicated by the Scoping Study will be
achieved. Investors should not make investment decisions based solely on the results of the Scoping Study.
Development of the Mt Lindsay Project will require substantial further funding. The Scoping Study estimates
pre-production capital of approximately A$244.5 million, before taking into account sustaining capital or
any additional funding requirements that may arise in connection with working capital, financing or other
development requirements. The Company has not secured any of that funding required to develop the
Project. Investors should note that there are risks that the Company will not be able to raise that amount of
funding when needed (or at all). Any future development funding may include (without limitation) one or a
combination of debt, equity, strategic partner, offtake-linked, joint venture or other commercial
arrangements. The Company considers that it has reasonable grounds to believe that the necessary project
funding may be obtainable as and when required, having regard to the matters described under “Project
Financing, Marketing and Offtake” in this announcement. There is no certainty that such funding will be
available when required or on acceptable terms. If equity funding is required, or if other funding
arrangements involve the issue of securities or project-level interests, this may dilute existing shareholders
or otherwise affect the value of their interests.
3
Executive Summary
• Scoping Study outlines a 1.0 Mtpa underground development pathway for the 100%-owned
Mt Lindsay Tin-Tungsten Project in north-west Tasmania.
• 100%-owned Project located in an established Tasmanian mining region and held under
granted Mining Lease.
• Base Case economics demonstrate strong modelled outcomes, based on the Scoping Study
production target and material assumptions set out in this announcement, including:
o Pre-tax NPV of approximately A$1.42 billion and IRR of approximately 65%
o After-tax NPV of approximately A$1.01 billion and IRR of approximately 56%
o Estimated payback period of approximately 1.9 years
o Modelled life-of-mine sales revenue of approximately A$5.20 billion
• Capital-efficient development with estimated pre-production capital of approximately
A$244.5 million.
• Scoping Study includes a 13.5-year mining schedule, processing approximately 10.9 Mt and
ramping up to a nominal steady-state processing rate of approximately 1.0 Mtpa.
• Tungsten is the principal revenue contributor under the Base Case, accounting for
approximately 75% of modelled life-of-mine revenue, providing significant exposure to a
strategically important critical mineral.
• Owner-operated underground mine concept based on longhole open stoping with paste fill,
dual-decline access and conveyor material handling.
• Established infrastructure setting – located within an established Tasmanian mining region
with existing road access, proximity to Tasmania’s predominantly renewable electricity grid
and hydroelectric power infrastructure, and access to established export infrastructure at
Burnie.
• Underground development represents a material departure from the historical open-pit
development approach, with the Study seeking to minimise additional surface disturbance
through project design and incorporating paste backfill to reduce the quantity of tailings
requiring permanent surface storage.
• Potential upside from copper and other by-products, which are excluded from the current
Scoping Study economics and remain subject to further evaluation.
• Critica is also progressing the Jupiter Rare Earth Project Scoping Study, which is targeted for
release shortly.
4
Key Financial Outputs
Metric Unit Base Case
Sales revenue A$m 5,204.2
Average annual EBITDA1 A$m 268.9
Pre-tax NPV A$m 1,415.6
After-tax NPV A$m 1,006.0
Pre-tax IRR % 64.9
After-tax IRR % 55.6
Payback period years 1.92
Pre-production capital A$m 244.5
After-tax NPV / pre-production capital² 4.1x
Total LOM capital (incl. sustaining capital and closure) A$m 441.8
Mining Schedule years 13.5
Processing schedule years 11.6
Material processed Mt 10.9
Notes: NPV is calculated using an 8% discount rate. All financial and operating figures presented in this table are
estimates based on Scoping Study-level assumptions and are approximate. The financial outcomes are derived from
the Scoping Study production target and should be read together with the material assumptions and cautionary
statements contained in this announcement.
1
Average annual EBITDA represents total modelled EBITDA divided by the modelled processing/revenue period and is
an arithmetic life-of-mine average. It does not represent forecast EBITDA in any individual year.
² After-tax NPV / pre-production capital is calculated by dividing after-tax NPV8 by estimated pre-production capital.
The Scoping Study production target comprises approximately 10.9 Mt of scheduled run-of-mine material
after applying mining modifying factors, of which approximately 92% is derived from Indicated Mineral
Resources and approximately 8% from Inferred Mineral Resources. There is a low level of geological
confidence associated with Inferred Mineral Resources and there is no certainty that further exploration
work will result in the determination of Indicated Mineral Resources or that the production target itself will
be realised.
Key Investment and Strategic Themes
1. Strong modelled economics – The Base Case generates a modelled after-tax NPV₈ of
approximately A$1.01 billion, an after-tax IRR of approximately 56% and an estimated
payback period of approximately 1.9 years, calculated on an after-tax, pre-finance basis from
the commencement of commercial production, based on a 13.5-year mining schedule.
2. Capital-efficient development – Pre-production capital of approximately A$244.5 million
provides a comparatively modest upfront capital requirement for the scale and duration of the
development scenario evaluated in the Scoping Study.
5
3. Strategic tungsten exposure – Tungsten is the principal revenue contributor under the Base
Case, accounting for approximately 75% of modelled life-of-mine revenue, providing
substantial exposure to a strategically important critical mineral with highly concentrated global
supply.
4. Predominantly Indicated production target in an established mining jurisdiction –
Approximately 92% of the Scoping Study production target is derived from Indicated Mineral
Resources, with approximately 8% derived from Inferred Mineral Resources. The Project is held
under a granted Mining Lease in an established Tasmanian mining district.
The forecast financial information should be read together with the Scoping Study cautionary statement
and material assumptions contained in this announcement.
Mt Lindsay provides Critica with material exposure to tin and tungsten, two strategically important metals
with established applications across electronics, semiconductors, solder, defence, cutting tools and
advanced manufacturing. In particular, the concentrated nature of global tungsten supply and its
importance to defence and advanced industrial applications supports the strategic relevance of potential
new sources of supply from jurisdictions such as Australia.
Tungsten is the principal revenue contributor under the Base Case, accounting for approximately 75% of
modelled life-of-mine revenue and providing Mt Lindsay with substantial exposure to a strategically
important critical mineral.
Global tungsten supply is highly concentrated, with China controlling approximately 79% of mining
capacity and 85% of APT refining capacity. S&P Global estimates a 21,000-tonne WO₃ supply gap outside
China in 2026 (August 2026). China's tungsten export controls, together with US defence procurement
restrictions extending across the supply chain from January 2027, represent a structural shift in global
supply that could underpin sustained higher prices rather than a cyclical spike.
As illustrated below, the European APT tungsten benchmark increased by more than 400% between
September 2025 and August 2026. This significant price appreciation has strengthened the prevailing
market backdrop for Mt Lindsay, noting that the Base Case assumes a tungsten APT price of
US$2,500/mtu.
The Scoping Study economics are based solely on the Main and No.2 deposits and exclude copper as a
payable product. Copper and other potential by-products provide potential upside but are excluded from
the current Scoping Study economics and remain subject to further mineralogical, metallurgical and
commercial evaluation. The Base Case APT price assumption of US$2,500/mtu is below the latest
European APT benchmark price shown in Figure 1.
Figure 1 | European APT Tungsten Benchmark Price – September 2025 to August 2026
Figure 1: European APT 88.5% WO₃ benchmark price. Source: Asian Metal. Benchmark: APT 88.5% WO₃ minimum,
CIF Rotterdam/Baltimore, duty-free, quoted in US$/mtu WO₃ Date Published 1 September 2026.
6
Pathway to Development
Mt Lindsay has a number of important foundations already in place to support its advancement toward a
Definitive Feasibility Study (DFS):
• 100% ownership and granted Mining Lease – providing a clear project ownership and tenure
position;
• Established Mineral Resource – supported by extensive historical drilling and technical work;
• Established mining region – located in Tasmania’s west coast mining district, close to existing
mining operations and services;
• Existing infrastructure and access – road access and proximity to Tasmania’s predominantly
renewable electricity grid, including established hydroelectric power infrastructure, and regional
rail infrastructure; and
• Access to export infrastructure – Burnie, approximately 120 km by road from the Project,
provides access to an established export port.
Figure 2 | Mt Lindsay location and regional infrastructure
Resource foundation
The updated JORC 2012 Mineral Resource for Mt Lindsay comprises 19 Mt @ 1.09% SnEq, containing
approximately 49 kt of tin and 28 kt of WO₃ at the primary 0.4% SnEq cut-off (refer ASX announcement
“Critica Updates Mt Lindsay Tin-Tungsten Mineral Resource to JORC 2012”, 14 September 2026). The
Scoping Study evaluates a subset of this Mineral Resource, with the production target comprising
approximately 10.9 Mt of scheduled run-of-mine material sourced solely from the Main and No.2
deposits.
Approximately 92% of the production target is derived from Indicated Mineral Resources and
approximately 8% from Inferred Mineral Resources after applying mining modifying factors. The Inferred
Mineral Resources are predominantly scheduled in the later years of the mine plan, with only limited
Inferred material scheduled in earlier years, and are not a determining factor in the viability of the
development scenario.
7
Underground development concept
The Scoping Study represents a material shift from the historical open-pit development concept
evaluated by the Company (formerly Venture Minerals Limited) in its 2012 Bankable Feasibility Study. The
preferred development concept evaluated by the Scoping Study comprises an owner-operated, 1.0 Mtpa
underground mine using longhole open stoping with paste fill, dual-decline access and conveyor material
handling.
The underground approach provides the basis for an integrated project configuration designed around
mine access, materials handling, processing infrastructure and tailings management. The Main and No.2
deposits are located completely beneath the surface, with the conceptual development providing
underground access from the existing HEC quarry area and conveyor material handling to the proposed
processing plant and tailings storage area, in proximity to the sealed Pieman Road and existing power
infrastructure.
Paste backfill forms an integral part of the underground mining concept, supporting the selected mining
method while reducing the quantity of tailings requiring permanent surface storage. The Study has also
sought, where practical, to utilise existing disturbed areas and infrastructure corridors to minimise
additional surface disturbance.
Figure 3 | Conceptual Mt Lindsay underground development and integrated surface infrastructure
Figure 3: Conceptual Mt Lindsay underground development and integrated surface infrastructure layout
showing the Main and No.2 deposits completely beneath the surface, underground access from the
existing HEC quarry and the relationship to proposed surface infrastructure.
Indicative development pathway
The Company’s current indicative development pathway contemplates advancing Mt Lindsay from the
Scoping Study into a Definitive Feasibility Study, with environmental assessment and approvals work,
metallurgical validation, product qualification and commercial engagement progressing in parallel.
Subject to successful completion of this work, receipt of required approvals, securing the required
project funding and a future Board decision to proceed, the Project would then progress through final
investment decision, construction, commissioning and production ramp-up. The timing of these
activities is indicative only and will be refined as the Project advances through subsequent study phases.
8
Figure 4 | Indicative Mt Lindsay development pathway
Note: The development timeline is indicative only and represents the Company’s current planning
assumptions. Timing is subject to successful completion of further studies and engineering,
environmental and regulatory approvals, product qualification and commercial outcomes, securing the
required project funding and a future Board decision to proceed. There is no certainty that the Project will
progress in accordance with this timeframe.
Next steps
Critica’s next phase of work will focus on the key workstreams required to further de-risk and advance Mt
Lindsay toward a Definitive Feasibility Study (DFS):
• Resource confidence – improved metallurgical characterisation to refine resource
classification;
• Mine design – further optimisation of the underground mine plan and schedule;
• Metallurgy – validation and optimisation of recoveries and product specifications;
• Engineering and infrastructure – further definition of key project infrastructure and logistics;
• Environmental and approvals – advancement of environmental studies and permitting
requirements; and
• Commercial and funding – advancement of funding strategy, offtake opportunities and potential
strategic partnerships.
Project Financial Forecasts
Economic analysis
The Base Case generates a modelled after-tax NPV₈ of approximately A$1.01 billion and an after-tax IRR
of approximately 56%. The key project valuation metrics are summarised below.
The Scoping Study economic analysis is based on the selected 1.0 Mtpa development case and
incorporates the mine schedule, metallurgical recoveries, capital and operating cost estimates and
commercial assumptions described in this announcement.
These financial outcomes are derived from the Scoping Study production target and should be read
together with the material assumptions and cautionary statements contained in this announcement.
9
Table 1 | Economic Analysis
Metric Unit Base Case
Pre-tax NPV8 A$m 1,415.6
After-tax NPV8 A$m 1,006.0
Pre-tax IRR % 64.9
After-tax IRR % 55.6
Payback period1
years 1.92
Pre-production capital A$m 244.5
After-tax NPV / pre-production capital 4.1x
All financial figures presented in this table are estimates based on Scoping Study-level assumptions and are
approximate.
¹ Payback period is calculated on an after-tax, pre-finance basis from commencement of commercial production.
Capital Cost Estimate
The current Base Case financial model includes pre-production capital of approximately A$244.5 million.
In addition, approximately A$177.3 million of sustaining capital is incurred over the operating life,
together with approximately A$20.0 million of closure costs, resulting in total modelled life-of-mine
capital of approximately A$441.8 million.
The pre-production capital estimate includes approximately A$39.5 million of capitalised mining
operating costs, A$82.5 million of mining capital, A$94.0 million of plant, TSF and other capital and
A$28.5 million of contingency, resulting in total pre-production capital of approximately A$244.5 million.
Table 2 | Pre-Production Capital Cost Estimate
Capital cost estimate Unit Base Case
Capitalised mining operating costs A$m 39.5
Mining Capital A$m 82.5
Plant, TSF and other capital A$m 94.0
Contingency A$m 28.5
Total pre-production capital A$m 244.5
The capital cost estimate has been prepared to Scoping Study level, for which an overall accuracy range
of approximately -25% to +50% would normally be expected. Most process plant and infrastructure
capital is based on previous BFS-level work and is considered consistent with Class 4 accuracy
expectations, while the mining estimate has a lower level of definition and may remain at Class 5. The
overall capital estimate should therefore be considered within the Scoping Study-level accuracy range
stated above. The key physical and production metrics underpinning the Scoping Study production target
and financial model are summarised below.
10
Table 3 | Key Physical and Production Metrics
Key project metrics Unit LOM
Project scale and duration
Mining schedule years 13.5
Processing period years 11.6
Nominal steady-state processing rate Mtpa 1.0
Mining
Waste mined kt 1,672
Mineralised material mined kt 10,908
Sn grade % 0.18%
WO3 grade % 0.14%
DTR magnetic mass recovery¹ % 13.04%
Processing
Mineralised material processed kt 10,908
Tin (Sn) concentrate production2
dmt 31,626
Tungsten (WO3) concentrate production2
dmt 19,339
Magnetite concentrate production2
dmt 2,144,445
¹ DTR magnetic mass recovery represents the proportion of material recoverable as magnetite iron ore concentrate.
DTR Mass Recovery was estimated in the Main and No.2 Mineral Resource model using Davis Tube Recovery analyses
for approximately 90% of the composited assay intervals, with the remaining intervals estimated by regression from
magnetic susceptibility.
² Concentrate production figures are Scoping Study outputs derived from the production target and metallurgical
assumptions. Historical pilot-scale testwork on approximately 3 tonnes of representative Main and No.2 material
produced a 45% Sn concentrate at 72% overall tin recovery, a tungsten concentrate exceeding 66% WO₃ at 83%
overall tungsten recovery to APT, and a 65% Fe iron ore concentrate at 98% recovery. Further bulk and pilot
metallurgical testwork is in progress.
Operating Costs
The Base Case financial model includes estimated life-of-mine operating costs for mining, processing,
general and administration, product transport and selling, and royalties, as summarised below.
11
Table 4 | Life-of-Mine Operating Costs
Operating cost category Unit Base Case
Mining costs A$m 1,143.8
Processing costs A$m 411.5
G&A / site administration A$m 87.3
Product transport and selling A$m 179.7
Royalties A$m 267.7
Total Operating Costs A$m 2,090.0
To provide an indication of the operating cost attributable to tungsten production, the Scoping Study also
presents a derived unit operating cost after crediting modelled tin and magnetite revenue.
Table 5 | Indicative Tungsten Unit Operating Costs
Unit cost metric Unit Base Case
Operating cost net of tin and magnetite by-product credits¹ US$/mtu 314
¹ Calculated as life-of-mine mining, processing, G&A/site administration and product transport and selling costs, less
modelled tin and magnetite revenue, divided by modelled payable tungsten production of approximately 1.006 million
mtu, and converted to US dollars at the Base Case AUD/USD exchange rate of 0.65. This is a non-IFRS financial
measure derived from the Scoping Study financial model and is not intended to represent a C1 or AISC cost.
Key Financial Assumptions
The key commodity price, exchange rate, taxation and discount rate assumptions applied in the Base
Case are summarised below.
Table 6 | Key Financial Assumptions
Assumption Unit Base Case
Tin price US$/t Sn 45,000
Tungsten APT price US$/mtu APT 2,500
Magnetite concentrate price US$/dmt concentrate 115
AUD:USD exchange rate US$/A$ 0.65
Corporate tax rate % 30
Discount rate for NPV % 8
The Base Case adopts long-term commodity price assumptions considered appropriate for assessing the
underlying economics of the Mt Lindsay Project. These assumptions were developed with reference to a
range of market sources, including consensus pricing adopted by comparable listed tin and tungsten
companies, published market pricing and data from Asian Metal (asianmetals.com), and London Metal
Exchange (LME) pricing data for tin.
12
Commodity Price Assumptions
The Scoping Study adopts long-term price assumptions of US$2,500/mtu for tungsten APT and
US$45,000/t for tin, both at discounts to the referenced market benchmarks.
Tungsten: The assumed APT price of US$2,500/mtu is approximately 17% below the referenced European
benchmark of US$3,000/mtu. The benchmark is based on Asian Metal's APT 88.5% WO₃ minimum, CIF
Rotterdam/Baltimore, duty-free price series, as presented in Figure 1, published on 1 September 2026.
The Company's long-term pricing approach reflects concentrated global tungsten supply and increasing
interest in secure, non-Chinese sources.
Tin: The assumed tin price of US$45,000/t is approximately 18% below the LME cash settlement price of
US$54,725/t on 1 September 2026. The Company's long-term outlook reflects demand from electronics
and electrification, alongside potential supply constraints.
Both assumptions incorporate discounts to current market benchmarks and reflect the Company's view
that structural supply constraints, rather than cyclical factors, alongside growing strategic and
technology-driven demand, will support longer-term prices.
Earnings and Cash Flow
The Scoping Study financial model generates substantial modelled earnings and free cash flow over the
life of the Project under the Base Case. The key modelled earnings and cash flow outcomes are
summarised below.
Table 7 | Earnings and Cash Flow
Financial metric Unit Base Case
Life-of-mine sales revenue A$m 5,204.2
Life-of-mine EBITDA A$m 3,114.3
Life-of-mine pre-tax free cash flow (FCFF)¹ A$m 2,672.4
Life-of-mine post-tax free cash flow (FCFF)¹ A$m 1,917.1
¹ Free cash flow to firm (FCFF) represents modelled project cash flow before financing and includes pre-production
and sustaining capital and closure costs.
Sensitivity analysis
The Base Case economics are sensitive to movements in commodity prices, ore grades, operating costs,
mining costs, upfront and sustaining capital, processing costs and waste tonnes. The sensitivity analysis
has been prepared against the Base Case after-tax NPV₈ of approximately A$1.01 billion and illustrates
the impact of independent ±10% and ±20% changes in each variable.
The analysis indicates that project value is most sensitive to commodity prices and ore grades. A 20%
reduction in commodity prices reduces after-tax NPV₈ to approximately A$614 million, while a 20%
reduction in ore grades reduces it to approximately A$625 million. Operating costs and mining costs also
have a material impact on project value, while upfront capital, processing costs, waste tonnes and
sustaining capital have a comparatively smaller effect within the ranges tested.
13
Figure 5 | Base Case After-Tax NPV8 sensitivity analysis
Figure 5: Base Case after-tax NPV₈ sensitivity analysis. Base Case NPV₈: A$1,006.0 million. Sensitivities show the
independent impact of ±10% and ±20% changes in each variable, with all other assumptions held constant.
The sensitivity analysis is illustrative only and considers changes to individual assumptions in isolation,
with other assumptions held constant. Actual project outcomes may be affected by simultaneous
changes in multiple variables and may differ materially from the outcomes presented.
Property description, access and infrastructure setting
Mt Lindsay is located in north-west Tasmania, approximately 32 kilometres by road west of Tullah and
approximately 120 kilometres by road from the Port of Burnie. The Project is located within an established
Tasmanian mining region that includes the Renison Bell and Rosebery mining operations.
The Project is accessed from the regional road network and existing access corridors. The Port of Burnie
provides established port infrastructure in north-west Tasmania, with any future use by the Project
subject to detailed logistics assessment and relevant commercial arrangements. Regional rail
infrastructure, including the Melba rail line, may provide a potential alternative transport option subject to
future project requirements and detailed assessment.
The physical set