Sale of Riley Mine and Updated Tasmanian Exit Strategy
Released
Released
Announcement PDF
ASX Announcement
Monday, 24 June 2024
Sale of the Riley Iron Ore Mine and Updated Tasmanian Strategy
The Board of Venture Minerals Ltd (ASX: VMS) (Venture or the Company) is pleased to announce
that it has entered into a share purchase and sale agreement (Sale Agreement) with Goldvalley
Brown Stone Pty Ltd (Gold Valley) for the sale of Venture’s wholly owned subsidiary, Venture Iron Pty
Ltd (Venture Iron), the holder of the Riley Iron Ore Mine (Project) located in Tasmania.
The Company engaged Argonaut PCF as advisors to undertake a strategic review of the Project,
which has been on care and maintenance since 2021. The review considered all options, including a
potential restart, joint venture or asset sale, with the focus on delivering near-term value for the
Company and its shareholders. The Company carefully considered all options presented and
following a competitive process determined that the sale of the Project was the best pathway to
unlock the commercial value for Venture shareholders.
The completion of the sale of the Project will bolster the Company cash reserves, allowing Venture to
unlock the full economic potential of the exciting new Jupiter Rare earth discovery.
The Company's existing cash reserves of approximately $1.6m will be strengthened by the receipt of
$3m, ten days after execution and $585k on return of the bank guarantee held by Mineral Resources
Tasmania.
Philippa Leggat, commented,
“The refreshed board is focussed on creating shareholder value. The sale of
Riley sees Venture receiving three million dollars and our environmental bond
of over half-a-million dollars being returned to the Company. This capital
injection will be used to advance our high-grade, clay-hosted rare earth
project, Jupiter. This also frees our team to focus their efforts on advancing
Jupiter while eliminating the financial burden of maintaining the Riley Project
on care and maintenance. We thank the Tasmanian Authorities for working
with Venture for all these years.”
About the Riley Transaction
The Sale Agreement does not contain any conditions precedent, and completion is expected to occur
on 8 July 2024 (being ten business days following entry into the Sale Agreement).
Upon completion under the Sale Agreement, the Company will transfer 100% of the shares in Venture
Iron to Gold Valley in consideration for $3,000,000 (of which $50,000 has already been paid to the
Company as a deposit).
Following completion, Gold Valley and the Company will work together to transfer various
governmental approvals required for the continued operation of the Project. Importantly, Gold Valley
will replace the Company’s bank guarantee ($585,000) currently held by Mineral Resources
Tasmania in connection with the mining licence.
The Sale Agreement contains terms, conditions and warranties that are consistent with agreements of
this nature. Gold Valley will fund the consideration through cash reserves. Venture is satisfied with
Gold Valley’s capacity to complete the Sale Agreement.
Page 1
ASX Announcement
Monday, 24 June 2024
Argonaut PCF will receive $250,000 in success fees and have the right to subscribe for 25m
options with an exercise price at a 50% premium to the Company’s 15-day volume weighted
average price per share immediately prior to an announcement of the Transaction.
Transaction Considerations
The following factors, among others, were considered reasons against the restart of the Project:
•
additional capital required;
•
the requirement to hire a team of specialist mining professionals with the capability to
successfully execute the Project;
•
the costs associated with hiring the additional staff members;
•
the short mine life of the Project being circa 18 months, with the reserve being geologically
constrained (no exploration upside);
•
the marginal nature of the Project economics, as the Project is low-grade and requires high
handling (low payability with relatively high operating costs); and
•
the outlook for iron ore pricing not being sufficiently buoyant to validate the degree of
associated risk presented by an operation of this nature.
In light of these considerations, the Board viewed the opportunity cost of diverting Venture’s
limited resources away from Jupiter and towards these factors as being detrimental to shareholder
value.
Tasmanian Strategy
The recently reconstituted Board believes that there is significant potential to increase shareholder
value by focussing the Company's capital and resources on its rare earths' assets, including the
exciting new discovery at Jupiter in Western Australia.
Consequently, the Company intends to appoint an advisor to run a sale process for its remaining
Tasmanian assets, namely the Mt Lindsay and Mt Livingston projects.
Authorised by the Board of Venture Minerals.
Philippa Leggat
Philippa Leggat
Managing Director
Page 2
ASX Announcement
Monday, 24 June 2024
About Gold Valley
Gold Valley companies are a multi-sector conglomerate consisting of interests in mining and energy.
Based in Perth, Gold Valley companies are supported by an experienced executive team and is
chaired by Mr Yuzheng Xie. No matter what sector and which project, GV’s activities are always
undertaken with the safety, environment and social “5 Pillars” to ensure the best possible outcome for
the environment, stakeholders and the community.
Gold Valley recently acquired:
•
the Wiluna West Iron Ore Project, which has a 130-million-tonne resource, from GWR Group
Limited (ASX:GWR) having operated the C4 iron ore deposit (a deposit within the Wiluna West
Iron Ore Project) since July 2022. Production is expected to increase to over 3 million tonnes
by the end of the year, utilising access through the Ports of Esperance and Geraldton; and
•
the life of mine hematite extraction rights over the Ularring Hematite Project from Macarthur
Minerals Limited (TSVX:MIO) (OTCQB:MMSDF).
Gold Valley in Tasmania:
Gold Valley is the majority shareholder (~79%) of Blythe River Iron Pty Ltd which owns a project
known as Hampshire 2 on EL 18/2007 covering a 63 km2 area near Hampshire, approximately 30 km
south-southwest of Burnie on Tasmania's northwest coast. Exploration focuses on the L13 and St.
Valentine’s Peak targets. Previous drilling has identified a magnetite skarn deposit with associated
scheelite that is of economic interest. The 2023-24 diamond drilling campaign completed by Blythe
River Iron Pty Ltd successfully extended the iron mineralisation footprint at the L13 prospect.